On May 10, 2008, Plano ISD voters approved a $490 million bond program. Initiatives were recommended by a 20-member bond task force established by the Plano ISD Board of Trustees and chaired by Phil Dyer and Ann Boswell (alternate chair).
Task force charge:
• Conduct comprehensive analysis of facilities needs, including onsite reviews of previous and proposed projects.
• Review future enrollment trends and projections.
• Establish construction, renovation and site acquisition needs.
• Validate cost projections to meet analyzed needs, taking into account inflationary trends.
• Review needs for technology and other capital items. |
|
Pre-Funded Projects - $27.8 Million
Schell Elementary School, Employee Child Care Center, Land Acquisitions
*Capital Improvements- $140.8 Million
• Sara Isaacs Early Childhood School (to complete fall 2009)
• Barron Conversion to elementary school (to complete fall 2009)
• New Elementary School (TBD)
• Dr. Douglas W. Otto Middle School (to complete fall 2010)
• New High School (to complete fall 2011)