Board Agenda - December 11, 2007
2. Christie Elementary Roof Replacement, #1 Project close-out
Presenter: Richard Matkin
Purpose: A - Request decision - closure required
Time: No time limit
Description:
This Change reconciles the allowance balance remaining in the project.
The Work of this Contract has been completed, the required closeout documentation is being completed and the Project is ready for Final Acceptance.
Summary:
Original Contract Amount: $845,000.00
Previous approved Change Orders: $0.00
Contract Amount prior to this Change Order: $845,000.00
This Change Order amount: $ (13,206.00)
Contract Amount after this Change Order: $831,794.00
Recommendation:
The Administration recommends that Change Order No. 1 in the deductive amount of $13,206.00 be approved. The Architect has reviewed this Change Order, and he concurs with the amount. The Administration also recommends that the work for the Christie Elementary Roof Replacement be accepted and that final payment, including the release of retainage, be made to BRI Roofing & Sheet Metal, Inc.
Business Impact:
Estimated Value: ($13,206.00)
Budget/Financial Implication: 2004 Bond Funds
Summary:
Appendix: