Project Architect Delivery Method
Christie ES Re-Roof SHW Group Competitive Sealed Proposal
Guinn Center Re-Roof SHW Group Competitive Sealed Proposal
Service Center Re-Roof WRA Architects Competitive Sealed Proposal
Recommendation:
The Administration recommends that the listed architects and construction delivery methods for the projects listed be approved.