Board Agenda : April 01, 2008 : Plano
Board Agenda - April 01, 2008
5. CSP #2007-065 - Hendrick Middle School Renovations Construction Manager at Risk and Guaranteed Maxim
Presenter: Richard Matkin
Purpose: A - Request decision - closure required
Time: No time limit
Description:
Cadence McShane Corporation was approved by the Board as the Construction Manager at Risk (CMR) on November 6, 2007. An early release package (Bid Package 1) for $598,983.00 was approved on March 4, 2008. At that time, the Construction Manager presented an Initial GMP estimate of $14,098,368.00.
The CMR has taken bids for the remaining work (Bid Package 2) and is presenting a total GMP for the entire project. Approval of the Bid Package 2 amount of $12,054,841.00 is being requested at this time. Adding this amount to the previously approved amount brings the total GMP for the entire project to $12,653,824.00. By the contractual definition, the Construction Manager's Fee for Construction Period Services is a part of the Guaranteed Maximum Price, and the Pre-Construction Period Services are outside the GMP. The summary below represents the allocation as it will be shown in the contract.
Pre- Construction Services Fee (previously approved): $10,000.00
Bid Package 1 (previously approved): $598,983.00
B
id Package 2 (this request for approval): $12,054,841.00
Guaranteed Maximum Price (includes previously
approved Construction Services Fee at 3.35%): $12,653,824.00
Construction Budget: $12,712,000.00
Total Contract Amount (including Pre-Construction Services): $12,663,824.00
Recommendation:
The Administration recommends that the Contract for Construction Manager at Risk with Cadence McShane Corporation be amended by an additional $12,054,841.00 to provide a Guaranteed Maximum Price of $12,653,824.00.
Business Impact:
Funding Source is 2004 Bond Funds: $12,663,824.00
Summary:
Appendix:
Return to Meeting Agenda
|
|