Plano Independent School District Calendar En Espaņol Site Index
Home About Us Schools Employment News for Parents for Students for Staff
 
Board Agenda : August 07, 2007 : Plano
About Us
Know Your School District
2008-2012
Strategic Plan
Annual Report
Awards & Ratings
Board of Trustees
Leadership Team
Service Departments
Directory of Schools
& Other Facilities
Budget Information
Instructional Program
Policies & Regulations
Purchasing Services
Safety & Security
Advisory Committees
Key Communicators
Education Foundation
Partners & Volunteers
About Plano
Contacts



Board Agenda - August 07, 2007

1. Clark Stadium Pressbox renovation #1

Presenter: Richard Matkin

Purpose: A - Request decision - closure required

Time: No time limit

Description:

This Change Order provides for a revision to the fire protection sprinkler system serving the Pressbox. The original design included a motor and pump to raise water to the top of the Pressbox for the fire protection system. The design team continued to work with the City code requirements as the construction was underway. While the new design required some rework and a change of pipe size, it now provided the required fire protection without the use of any motors or pumps. This is a benefit to the District in the long term by eliminating the regular maintenance and replacement costs for the motor and pump.

The Contract Time is also being extended to August 13, 2007 by the work of this Change Order. This new date of Substantial Completion is still prior to the first scheduled use of the facility.

The Architect for the work has reviewed the pricing and has prepared and executed the Change Order form. The Contractor has executed the Change Order form.

Summary:
Original Contract Amount: $ 3,573,522.00
Previous Approved Change Orders: $ 0.00
Contract Amount prior to this Change Order $ 3,573,522.00
This Change Order Amount: $ 59,758.00
Contract Amount After This Change Order: $ 3,633,280.00

Recommendation:

The Administration recommends that Change Order No. 1 to the construction contract for the Clark Stadium Renovation be approved in the amount of $59,758.00.

Business Impact:

Estimated Value: $ 59,758.00
Budget/Financial Implication: 2004 Bond Funds