Concrete Projects Less Than $25K - Bid # 3730

Vendors: GT
Construction
SFCC Awarded
To:
1 New Installation of Concrete:        
  Flatwork-per square ft. per jobsite     Primary
Vendor:
Secondary
Vendor:
1a 4" thick, cost per square foot when pouring 1-499 square feet $3.60 $4.00 GT
Construction
SFCC
1b 4" thick, cost per square foot when pouring 500-999 square feet $3.40 $3.75 GT
Construction
SFCC
1c 4" thick, cost per square foot when pouring 1000-2499 square feet $3.00 $3.50 GT
Construction
SFCC
1d 4" thick, cost per square foot when pouring 2500-7999 square feet $2.75 $3.45 GT
Construction
SFCC
1e 4" thick, cost per square foot when pouring over 8000 square feet $2.50 $3.42 GT
Construction
SFCC
1f 5" thick, cost per square foot when pouring 1-499 square feet $3.75 $4.50 GT
Construction
SFCC
1g 5" thick, cost per square foot when pouring 500-999 square feet $3.60 $4.35 GT
Construction
SFCC
1h 5" thick, cost per square foot when pouring 1000-2499 square feet $3.40 $4.15 GT
Construction
SFCC
1i 5" thick, cost per square foot when pouring 2500-7999 square feet $3.20 $4.12 GT
Construction
SFCC
1j 5" thick, cost per square foot when pouring over 8000 square feet $3.00 $4.10 GT
Construction
SFCC
1k 6" thick, cost per square foot when pouring 1-499 square feet $3.95 $4.75 GT
Construction
SFCC
1l 6" thick, cost per square foot when pouring 500-999 square feet $3.75 $4.60 GT
Construction
SFCC
1m 6" thick, cost per square foot when pouring 1000-2499 square feet $3.60 $4.50 GT
Construction
SFCC
1n 6" thick, cost per square foot when pouring 2500-7999 square feet $3.30 $4.45 GT
Construction
SFCC
1o 6" thick, cost per square foot when pouring over 8000 square feet $3.10 $4.40 GT
Construction
SFCC
1p 7" thick, cost per square foot when pouring 1-499 square feet $4.00 $5.45 GT
Construction
SFCC
1q 7" thick, cost per square foot when pouring 500-999 square feet $3.80 $5.30 GT
Construction
SFCC
1r 7" thick, cost per square foot when pouring 1000-2499 square feet $3.70 $5.28 GT
Construction
SFCC
1s 7" thick, cost per square foot when pouring 2500-7999 square feet $3.40 $5.26 GT
Construction
SFCC
1t 7" thick, cost per square foot when pouring over 8000 square feet $3.20 $5.25 GT
Construction
SFCC
           
2 Curbs - per lineal ft. per jobsite        
2a 2-9 linear foot $19.00 $36.00 GT
Construction
SFCC
2b 10-25 linear foot $16.00 $24.00 GT
Construction
SFCC
2c Over 25 linear foot $14.00 $16.00 GT
Construction
SFCC
           
3 Curbs - free standing (6"x12")        
3a 2-9 linear foot $23.00 $24.00 GT
Construction
SFCC
3b 10-25 linear foot $20.00 $18.00 GT
Construction
SFCC
3c Over 25 linear foot $16.00 $12.00 GT
Construction
SFCC
           
4 Flatwork - per square foot per job site        
4a 4" thick, cost per square foot when pouring 1-499 square feet $4.85 $6.50 GT
Construction
SFCC
4b 4" thick, cost per square foot when pouring 500-999 square feet $4.80 $6.25 GT
Construction
SFCC
4c 4" thick, cost per square foot when pouring 1000-2499 square feet $4.60 $6.00 GT
Construction
SFCC
4d 4" thick, cost per square foot when pouring 2500-7999 square feet $4.35 $5.95 GT
Construction
SFCC
4e 4" thick, cost per square foot when pouring over 8000 square feet $4.00 $5.92 GT
Construction
SFCC
4f 5" thick, cost per square foot when pouring 1-499 square feet $4.95 $7.00 GT
Construction
SFCC
4g 5" thick, cost per square foot when pouring 500-999 square feet $4.90 $6.85 GT
Construction
SFCC
4h 5" thick, cost per square foot when pouring 1000-2499 square feet $4.70 $6.65 GT
Construction
SFCC
4i 5" thick, cost per square foot when pouring 2500-7999 square feet $4.40 $6.62 GT
Construction
SFCC
4j 5" thick, cost per square foot when pouring over 8000 square feet $4.10 $6.60 GT
Construction
SFCC
4k 6" thick, cost per square foot when pouring 1-499 square feet $5.10 $7.75 GT
Construction
SFCC
4l 6" thick, cost per square foot when pouring 500-999 square feet $5.00 $7.60 GT
Construction
SFCC
4m 6" thick, cost per square foot when pouring 1000-2499 square feet $4.90 $7.50 GT
Construction
SFCC
4n 6" thick, cost per square foot when pouring 2500-7999 square feet $4.50 $7.45 GT
Construction
SFCC
4o 6" thick, cost per square foot when pouring over 8000 square feet $4.30 $7.40 GT
Construction
SFCC
4p 7" thick, cost per square foot when pouring 1-499 square feet $5.20 $8.45 GT
Construction
SFCC
4q 7" thick, cost per square foot when pouring 500-999 square feet $5.10 $8.30 GT
Construction
SFCC
4r 7" thick, cost per square foot when pouring 1000-2499 square feet $5.00 $8.28 GT
Construction
SFCC
4s 7" thick, cost per square foot when pouring 2500-7999 square feet $4.60 $8.26 GT
Construction
SFCC
4t 7" thick, cost per square foot when pouring over 8000 square feet $4.55 $8.25 GT
Construction
SFCC
           
5 Curbs - per lineal foot per jobsite        
5a 2-9 linear foot $30.00 $46.00 GT
Construction
SFCC
5b 10-25 linear foot $27.00 $34.00 GT
Construction
SFCC
5c Over 25 linear foot $23.00 $24.00 GT
Construction
SFCC
           
6 Slope Paving        
6a 4" thick, cost per square foot when pouring 1-499 square feet $3.60 $7.50 GT
Construction
SFCC
6b 4" thick, cost per square foot when pouring 500-999 square feet $3.50 $7.25 GT
Construction
SFCC
6c 4" thick, cost per square foot when pouring 1000-2499 square feet $3.30 $7.00 GT
Construction
SFCC
6d 4" thick, cost per square foot when pouring 2500-7999 square feet $3.25 $6.95 GT
Construction
SFCC
6e 4" thick, cost per square foot when pouring over 8000 square feet $3.15 $6.92 GT
Construction
SFCC
6f 5" thick, cost per square foot when pouring 1-499 square feet $3.65 $8.00 GT
Construction
SFCC
6g 5" thick, cost per square foot when pouring 500-999 square feet $3.55 $7.85 GT
Construction
SFCC
6h 5" thick, cost per square foot when pouring 1000-2499 square feet $3.40 $7.65 GT
Construction
SFCC
6i 5" thick, cost per square foot when pouring 2500-7999 square feet $3.40 $7.62 GT
Construction
SFCC
6j 5" thick, cost per square foot when pouring over 8000 square feet $3.20 $7.60 GT
Construction
SFCC
6k 6" thick, cost per square foot when pouring 1-499 square feet $3.70 $8.75 GT
Construction
SFCC
6l 6" thick, cost per square foot when pouring 500-999 square feet $3.60 $8.60 GT
Construction
SFCC
6m 6" thick, cost per square foot when pouring 1000-2499 square feet $3.30 $8.50 GT
Construction
SFCC
6n 6" thick, cost per square foot when pouring 2500-7999 square feet $3.10 $8.45 GT
Construction
SFCC
6o 6" thick, cost per square foot when pouring over 8000 square feet $3.00 $8.40 GT
Construction
SFCC
           
7 Exterior Handicap Ramps        
7a 4" thick, cost per square foot when pouring 1-499 square feet $5.00 $9.50 GT
Construction
SFCC
7b 4" thick, cost per square foot when pouring 500-999 square feet $4.90 $7.00 GT
Construction
SFCC
7c 4" thick, cost per square foot when pouring 1000-2499 square feet $4.80 $6.50 GT
Construction
SFCC
7d 4" thick, cost per square foot when pouring 2500-7999 square feet $4.40 $6.00 GT
Construction
SFCC
7e 6" thick, cost per square foot when pouring 1-499 square feet $5.20 $9.50 GT
Construction
SFCC
7f 6" thick, cost per square foot when pouring 500-999 square feet $5.10 $7.00 GT
Construction
SFCC
7g 6" thick, cost per square foot when pouring 1000-2499 square feet $5.00 $7.00 GT
Construction
SFCC
7h 6" thick, cost per square foot when pouring 2500-7999 square feet $4.60 $6.80 GT
Construction
SFCC
           
8 Interior Handicap Ramps        
8a 4" thick, cost per square foot when pouring 1-499 square feet $6.00 $9.50 GT
Construction
SFCC
8b 4" thick, cost per square foot when pouring 500-999 square feet $5.90 $7.00 GT
Construction
SFCC
8c 4" thick, cost per square foot when pouring 1000-2499 square feet $5.80 $6.50 GT
Construction
SFCC
8d 4" thick, cost per square foot when pouring 2500-7999 square feet $5.40 $6.00 GT
Construction
SFCC
8e 6" thick, cost per square foot when pouring 1-499 square feet $6.20 $9.50 GT
Construction
SFCC
8f 6" thick, cost per square foot when pouring 500-999 square feet $6.10 $7.00 GT
Construction
SFCC
8g 6" thick, cost per square foot when pouring 1000-2499 square feet $5.90 $7.00 GT
Construction
SFCC
8h 6" thick, cost per square foot when pouring 2500-7999 square feet $5.75 $6.80 GT
Construction
SFCC
           
9 Interior Pour - square foot per job site. New installation of concrete inside of buildings        
9a 4" thick, cost per square foot when pouring 1-499 square feet $5.50 $7.50 GT
Construction
SFCC
9b 4" thick, cost per square foot when pouring 500-999 square feet $5.45 $7.40 GT
Construction
SFCC
9c 4" thick, cost per square foot when pouring 1000-2499 square feet $5.35 $7.30 GT
Construction
SFCC
9d 4" thick, cost per square foot when pouring 2500-7999 square feet $5.10 $7.20 GT
Construction
SFCC
9e 4" thick, cost per square foot when pouring over 8000 square feet $4.90 $7.00 GT
Construction
SFCC
9f 5" thick, cost per square foot when pouring 1-499 square feet $5.60 $8.00 GT
Construction
SFCC
9g 5" thick, cost per square foot when pouring 500-999 square feet $5.55 $7.90 GT
Construction
SFCC
9h 5" thick, cost per square foot when pouring 1000-2499 square feet $5.35 $7.80 GT
Construction
SFCC
9i 5" thick, cost per square foot when pouring 2500-7999 square feet $5.25 $7.70 GT
Construction
SFCC
9j 5" thick, cost per square foot when pouring over 8000 square feet $5.00 $7.50 GT
Construction
SFCC
9k 6" thick, cost per square foot when pouring 1-499 square feet $7.00 $8.75 GT
Construction
SFCC
9l 6" thick, cost per square foot when pouring 500-999 square feet $6.90 $8.65 GT
Construction
SFCC
9m 6" thick, cost per square foot when pouring 1000-2499 square feet $6.80 $8.50 GT
Construction
SFCC
9n 6" thick, cost per square foot when pouring 2500-7999 square feet $6.60 $8.40 GT
Construction
SFCC
9o 6" thick, cost per square foot when pouring over 8000 square feet $6.00 $8.30 GT
Construction
SFCC
9p 7" thick, cost per square foot when pouring 1-499 square feet $7.10 $9.45 GT
Construction
SFCC
9q 7" thick, cost per square foot when pouring 500-999 square feet $6.90 $9.25 GT
Construction
SFCC
9r 7" thick, cost per square foot when pouring 1000-2499 square feet $6.80 $9.10 GT
Construction
SFCC
9s 7" thick, cost per square foot when pouring 2500-7999 square feet $6.60 $9.05 GT
Construction
SFCC
9t 7" thick, cost per square foot when pouring over 8000 square feet $6.25 $9.00 GT
Construction
SFCC
           
10 Interior Pour - square foot per job site. Repair, removal of existing concrete & replacement w/ new concrete on interior of building.        
10a 4" thick, cost per square foot when pouring 1-499 square feet $7.50 $9.50 GT
Construction
SFCC
10b 4" thick, cost per square foot when pouring 500-999 square feet $7.40 $9.40 GT
Construction
SFCC
10c 4" thick, cost per square foot when pouring 1000-2499 square feet $7.20 $9.35 GT
Construction
SFCC
10d 4" thick, cost per square foot when pouring 2500-7999 square feet $7.00 $9.35 GT
Construction
SFCC
10e 4" thick, cost per square foot when pouring over 8000 square feet $6.50 $9.25 GT
Construction
SFCC
10f 5" thick, cost per square foot when pouring 1-499 square feet $7.70 $9.50 GT
Construction
SFCC
10g 5" thick, cost per square foot when pouring 500-999 square feet $7.60 $9.40 GT
Construction
SFCC
10h 5" thick, cost per square foot when pouring 1000-2499 square feet $7.40 $9.35 GT
Construction
SFCC
10i 5" thick, cost per square foot when pouring 2500-7999 square feet $7.20 $9.35 GT
Construction
SFCC
10j 5" thick, cost per square foot when pouring over 8000 square feet $7.00 $9.25 GT
Construction
SFCC
10k 6" thick, cost per square foot when pouring 1-499 square feet $7.80 $10.50 GT
Construction
SFCC
10l 6" thick, cost per square foot when pouring 500-999 square feet $7.70 $10.40 GT
Construction
SFCC
10m 6" thick, cost per square foot when pouring 1000-2499 square feet $7.60 $10.35 GT
Construction
SFCC
10n 6" thick, cost per square foot when pouring 2500-7999 square feet $7.40 $10.30 GT
Construction
SFCC
10o 6" thick, cost per square foot when pouring over 8000 square feet $7.30 $10.30 GT
Construction
SFCC
10p 7" thick, cost per square foot when pouring 1-499 square feet $8.00 $10.95 GT
Construction
SFCC
10q 7" thick, cost per square foot when pouring 500-999 square feet $7.90 $10.80 GT
Construction
SFCC
10r 7" thick, cost per square foot when pouring 1000-2499 square feet $7.80 $10.60 GT
Construction
SFCC
10s 7" thick, cost per square foot when pouring 2500-7999 square feet $7.50 $10.50 GT
Construction
SFCC
10t 7" thick, cost per square foot when pouring over 8000 square feet $7.40 $10.45 GT
Construction
SFCC
           
11 Concrete Saw-Cutting on exterior of Buildings        
11a 4" thick, cost per square foot when pouring 1-499 square feet $2.70 $3.90 GT
Construction
SFCC
11b 4" thick, cost per square foot when pouring 500-999 square feet $2.50 $3.00 GT
Construction
SFCC
11c 4" thick, cost per square foot when pouring 1000-2499 square feet $2.20 $3.00 GT
Construction
SFCC
11d 4" thick, cost per square foot when pouring 2500-7999 square feet $2.20 $3.00 GT
Construction
SFCC
11e 6" thick, cost per square foot when pouring 1-499 square feet $2.80 $4.50 GT
Construction
SFCC
11f 6" thick, cost per square foot when pouring 500-999 square feet $2.60 $4.00 GT
Construction
SFCC
11g 6" thick, cost per square foot when pouring 1000-2499 square feet $2.30 $4.00 GT
Construction
SFCC
11h 6" thick, cost per square foot when pouring 2500-7999 square feet $2.20 $4.00 GT
Construction
SFCC
           
12 Concrete Saw-Cutting on Interior of Buildings        
12a 4" thick, cost per square foot when pouring 1-499 square feet no bid $4.25 SFCC  
12b 4" thick, cost per square foot when pouring 500-999 square feet no bid $3.50 SFCC  
12c 4" thick, cost per square foot when pouring 1000-2499 square feet no bid $3.50 SFCC  
12d 4" thick, cost per square foot when pouring 2500-7999 square feet no bid $3.50 SFCC  
12e 6" thick, cost per square foot when pouring 1-499 square feet no bid $4.75 SFCC  
12f 6" thick, cost per square foot when pouring 500-999 square feet no bid $4.25 SFCC  
12g 6" thick, cost per square foot when pouring 1000-2499 square feet no bid $4.25 SFCC  
12h 6" thick, cost per square foot when pouring 2500-7999 square feet no bid $4.25 SFCC  
           
13 Breakout & Removal From Exterior of Buildings        
13a 4" thick, cost per square foot when pouring 1-499 square feet $2.50 $9.75 GT
Construction
SFCC
13b 4" thick, cost per square foot when pouring 500-999 square feet $2.40 $7.75 GT
Construction
SFCC
13c 4" thick, cost per square foot when pouring 1000-2499 square feet $2.10 $7.70 GT
Construction
SFCC
13d 4" thick, cost per square foot when pouring 2500-7999 square feet $2.00 $7.70 GT
Construction
SFCC
13e 6" thick, cost per square foot when pouring 1-499 square feet $2.70 $10.00 GT
Construction
SFCC
13f 6" thick, cost per square foot when pouring 500-999 square feet $2.50 $8.00 GT
Construction
SFCC
13g 6" thick, cost per square foot when pouring 1000-2499 square feet $2.20 $8.00 GT
Construction
SFCC
13h 6" thick, cost per square foot when pouring 2500-7999 square feet $2.10 $8.00 GT
Construction
SFCC
           
14 Breakout & Removal From Interior of Buildings        
14a 4" thick, cost per square foot when pouring 1-499 square feet $4.50 $10.00 GT
Construction
SFCC
14b 4" thick, cost per square foot when pouring 500-999 square feet $4.40 $8.75 GT
Construction
SFCC
14c 4" thick, cost per square foot when pouring 1000-2499 square feet $4.10 $8.70 GT
Construction
SFCC
14d 4" thick, cost per square foot when pouring 2500-7999 square feet $4.00 $8.70 GT
Construction
SFCC
14e 6" thick, cost per square foot when pouring 1-499 square feet $4.60 $10.20 GT
Construction
SFCC
14f 6" thick, cost per square foot when pouring 500-999 square feet $4.50 $8.90 GT
Construction
SFCC
14g 6" thick, cost per square foot when pouring 1000-2499 square feet $4.20 $8.85 GT
Construction
SFCC
14h 6" thick, cost per square foot when pouring 2500-7999 square feet $4.10 $8.85 GT
Construction
SFCC
           
15 Concrete Wall-Sawing (includes installation of headers & removal of all debris.)        
  Cost per linear foot no bid no bid no award no award
           
16 Concrete Core Drilling        
16a Drill thru 2" wall $175.00 $250.00 GT
Construction
SFCC
16b Drill thru 4" wall $175.00 $275.00 GT
Construction
SFCC
16c Drill thru 6" wall $185.00 $275.00 GT
Construction
SFCC
16d Drill thru 8" wall $200.00 $300.00 GT
Construction
SFCC
16e Drill thru 2" floor $225.00 $200.00 GT
Construction
SFCC
16f Drill thru 4" floor $235.00 $200.00 GT
Construction
SFCC
16g Drill thru 6" floor $260.00 $225.00 GT
Construction
SFCC
16h Drill thru 8" floor $275.00 $250.00 GT
Construction
SFCC
           
  Section II - Asphalt Paving Repair        
1 Skin patching, cost per ton: $250.00 no bid GT
Construction
 
2 Full depth type "D" asphalt surface patching to a depth of 6"-8", cost per ton     GT
Construction
 
2a Price per ton installed complete including: labor, materials, haul-off, blade work, soil sterilant. Cost per ton: $200.00 no bid GT
Construction
 
2b Price per ton for 2" base where needed: $175.00 no bid GT
Construction
 
           
3 Existing Asphalt pavements sealant coal tar pitch emulsion. Cost per square foot:        
3a Single seal Coat 0-500 square feet: $0.85 no bid GT
Construction
 
3b Single Seal Coat 501-1,000 square feet: $0.65 no bid GT
Construction
 
3c Single Seal Coat 1001-2,000 square feet:Single Seal Coat 501-1,000 square feet: $0.45 no bid GT
Construction
 
3d Single Seal Coat 2001-4,000 square feet:Single Seal Coat 501-1,000 square feet: $0.40 no bid GT
Construction
 
3e Single Seal Coat 4001-above square feet $0.35 no bid GT
Construction
 
3f Double seal Coat 0-500 square feet: $0.30 no bid GT
Construction
 
3g Double Seal Coat 501-1,000 square feet: $0.25 no bid GT
Construction
 
3h Double Seal Coat 1001-2,000 square feet:Single Seal Coat 501-1,000 square feet: $0.23 no bid GT
Construction
 
3i Double Seal Coat 2001-4,000 square feet:Single Seal Coat 501-1,000 square feet: $0.22 no bid GT
Construction
 
3j Double Seal Coat 4001-above square feet $0.20 no bid GT
Construction
 
           
4 Asphalt Sealing 2 applications of spray seal coat        
4a Asphalt Sealing 0-50 square yards $0.30 no bid GT
Construction
 
4b Asphalt Sealing 51-250 square yards $0.30 no bid GT
Construction
 
4c Asphalt Sealing 251-500 square yards $0.40 no bid GT
Construction
 
4d Asphalt Sealing 501-above square yards $0.50 no bid GT
Construction
 
           
5 New asphalt pavement structure 2" base lift & surface lift (total 4") on 6" compacted flexbase (95% SPD)        
5a Asphalt Paving 0-50 square yards $45.00 no bid GT
Construction
 
5b Asphalt Paving 51-250 square yards $40.00 no bid GT
Construction
 
5c Asphalt Paving 251-500 square yards $40.00 no bid GT
Construction
 
5d Asphalt Paving 501-above square yards $35.00 no bid GT
Construction
 
           
6 Patch existing 4" asphalt including: removal & disposal of existing        
6a Patch existing 0-50 square yards $30.00 no bid GT
Construction
 
6b Patch existing 51-250 square yards $27.50 no bid GT
Construction
 
6c Patch existing 251-500 square yards $25.00 no bid GT
Construction
 
6d Patch existing 501-above square yards $20.00 no bid GT
Construction
 
           
7 Cold pour asphalt crack sealant        
7a Cold pour crack seal 0-50 linear feet $2.50 no bid GT
Construction
 
7b Cold pour crack seal 51-500 linear feet $1.50 no bid GT
Construction
 
7c Cold pour crack seal 501-1,000 linear feet $1.00 no bid GT
Construction
 
7d Cold pour crack seal 1,001-5,000 linear feet $0.75 no bid GT
Construction
 
7e Cold pour crack seal 5,001-above linear feet $0.50 no bid GT
Construction
 
           
8 Hot pour asphalt crack sealant        
8a Hot pour crack seal 0-50 linear feet $2.75 no bid GT
Construction
 
8b Hot pour crack seal 51-above linear feet $2.22 no bid GT
Construction
 
           
9 Expansion joints & crack sealer        
9a 1/4" crack seal X 0-1000 linear feet $0.50 no bid GT
Construction
 
9b 1/4" crack seal X 1001-5000 linear feet $0.35 no bid GT
Construction
 
9c 1/4" crack seal X 5000-above linear feet $0.20 no bid GT
Construction
 
9d 1/2" crack seal X 0-1000 linear feet $0.75 no bid GT
Construction
 
9e 1/2" crack seal X 1001-5000 linear feet $0.50 no bid GT
Construction
 
9f 1/2" crack seal X 5001-above linear feet $0.40 no bid GT
Construction
 
9g 3/4" crack seal X 0-1000 linear feet $1.00 no bid GT
Construction
 
9h 3/4" crack seal X 1001-5000 linear feet $0.75 no bid GT
Construction
 
9i 3/4" crack seal X 50001-above linear feet $0.65 no bid GT
Construction
 
           
10 Saw cut asphalt 3"-4" thick per linear foot $1.75 $4.00 GT
Construction
SFCC
           
11 Primary contractor guaranteed response time to start each project (weather permitting) after receipt of a purchase order 3-5 days 2-5 days GT
Construction
SFCC
           
12 For all items not listed in this bid, please state percentage of up charge: 15.00% 15.00% GT
Construction
SFCC
           
  NO BIDS:        
  Benchmark, Inc.