2022 Bond & Construction Quarterly Update

In November 2022, Plano ISD voters approved a $1.34 billion bond package and a Voter-Approval Tax Rate Election (VATRE). The bond will allow the district to update schools and facilities, add additional safety measures, build a much needed CTE center, add ADA-accessible playgrounds at all elementary schools and more. For nearly a century, the Plano ISD community has shown a deep commitment to Plano schools. The 2022 bond election marks the 26th bond referendum passed by Plano ISD voters since 1923.

Construction Status Report

 

Plano Senior High School

2200 Independence Parkway, Plano, Texas 75075

  • Architect: Corgan
  • Contractor: CORE
  • Plano ISD Construction Administrator: Quincy Lara

Scope

Renovation of approximately 465,000 SF of existing buildings.  About 35,000 SF of addition for two new gym floors, weight room and locker room space.  Another 10,000 SF of new addition for front entry or where needed.  All buildings to be modernized, and major building systems upgraded.  Major remodel of Kitchen/Dining area. Campus will also receive updates to safety and security. Site athletic considerations include tennis court replacement/relocation along with storage and restrooms. Baseball and softball turf replacement, dugout extensions. 6’ wrought iron fence and gates around existing turf field and track. Auxiliary field LED lights.

Timeline

  • Design Initiated: 7/2023
  • Anticipated Design Completed: 8/2024
  • Expected Construction Started: 11/2024
  • Scheduled Construction Completed: 7/2028

Status

Programming meetings are wrapping up.  The architect began putting schematic blocks together to see how the pieces might all fit.  Square footage being requested is still a challenge as we aim to balance what is needed with the budget.  An early package will need to be presented to the Board so the new softball field can be built before the old one is taken down to make way for Haggard.

Estimated Construction Budget

$197,210,000

Proposed Lower Level Schematic
Proposed Lower Level Schematic 3/1/24

Existing Softball Needs to Move
Existing Softball Needs to Move  3/1/24


Early Childhood School Kitchen/Dining Additions

  • Architect: Glenn Partners
  • Contractor: MDI
  • Plano ISD Construction Administrator: Oscar Mojica

Scope

Kitchen/Dining room additions at each of the District’s three Early Childhood Schools.

  • Beaty ECS - 1717 Nevada Dr., Plano, Texas 75093
  • Isaacs ECS - 3400 E. Parker Rd., Plano, Texas 75074
  • Pearson ECS - 4000 Eagle Pass, Plano, Texas 75023

Construction will also include HVAC Controls, new digital marquees, and new chillers at Beaty and Pearson.   

Timeline

Design Initiated: 8/2023
Anticipated Design Completion: 4/2024
Expected Construction Start: 6/2024
Scheduled Construction Completion: 9/2025

Status

90% Construction Documents.  Initial 50% estimate needed a few clarifications which are anticipated will bring the numbers closer to budget.  Awaiting contractor’s 90% estimate.  Contractor is set to take out for bid with subs mid-April.  Will present a GMP to the Board May 21.     

Estimated Construction Budget

 Beaty:        $4,961,883
Isaacs:       $5,884,863
Pearson:    $5,220,997
 

Existing Isaacs Activity Room 12/1/23
Existing Isaacs Activity Room 12/1/23

Existing Beaty Dining
Existing Beaty Dining 12/1/23


Centennial Elementary School Kitchen Renovation/Addition

2609 Ventura Drive, Plano, Texas 75093

  • Architect: Stantec
  • Contractor: JC Commercial
  • Plano ISD Construction Administrator: Oscar Mojica

Scope

Major remodel of the kitchen, including additional space if needed, including all new equipment.  Systems and compliance items include new electrical panels, fire alarm replacement, new digital marquee, new restroom partitions and some sidewalk repair.  Security recommendations include exterior door position contacts, and additional play area fencing if viable.  Also adding two sinks at the art room.

Timeline

  • Design Initiated: 8/2023
  • Anticipated Design Completed: 2/2024
  • Expected Construction Started: 4/2024
  • Scheduled Construction Completed: 11/2024

Status

Opened bids February 13th from four bidders.  Evaluation team reviewed bids and recommended JC Commercial.  Anticipate starting construction in April.

Estimated Construction Budget

$3,062,777

Recent Hughston ES Kitchen Remodel
Recent Hughston ES Kitchen Remodel

Recent Saigling ES Serving Line Upgrade
Recent Saigling ES Serving Line Upgrade


Clark High School Structural Repair/Renovation

523 Spring Creek Parkway, Plano, Texas 75023

  • Architect: Corgan
  • Contractor: TBD (CSP)
  • Plano ISD Construction Administrator: Quincy Lara

Scope

Structural repairs of the special education area, two interior stairs, some sidewalks and a ramp along the east side of the building.  Also will look to replace the slabs and floors in both gyms.  In replacing the gym floors there is also the opportunity to follow athletic realignment.  Systems and compliance items include new controls, new cooling tower and some new RTUs.  Security recommendations include entry resistant film at main and secondary entries, emergency call stations, additional parking lot lighting, exterior door position contacts, and additional cameras.

Timeline

  • Design Initiated: 8/2023
  • Anticipated Design Completed: 8/2024
  • Expected Construction Started: 10/2024
  • Scheduled Construction Completed: 8/2025

Status

Corgan walked the site with consultants to inspect the existing conditions back in late February.  Still anticipate issuing bid documents the end of summer of 2024.  The contractor will procure materials in the winter and spring with construction being completed over the summer of 2025.

Estimated Construction Budget

$3,738,508

Replace Slabs in Both Gyms

Replace Slabs in Both Gyms

Sidewalk Repair Needed
Sidewalk Repair Needed


Haggard Middle School Replacement

2832 Parkhaven Drive, Plano, Texas 75075

  • Architect: VLK
  • Contractor: CORE
  • Plano ISD Construction Administrator: Quincy Lara

Scope

Construction of a new Haggard Middle School (Grades 6-8) approximately 187,900 SF.  It will be built on the existing site to replace the current campus. The existing building will remain in use during the construction of the project, and great care will be given to protect and maintain the present site, building, services, infrastructure, security and access.  Once the new building is complete the existing will be demolished.  Site conditions such as circulation drives, fire lanes, parking, and landscape/irrigation will be included in the work and overall plan along with a new 4-lane synthetic track. 

Timeline

  • Design Initiated: 7/2023
  • Anticipated Design Completed: 11/2024
  • Expected Construction Started: 2/2025
  • Scheduled Construction Completed:
    • New Building, paving and drives: 7/2026
    • Demo of the existing building, and building of new Track: 12/2026

Status

75% Construction Documents.  Anticipate bidding in November, and recommending a GMP to the January Board.  Construction to begin February 2025.

Estimated Construction Budget

$90,000,000

 

Haggard Middle School Site Map

Proposed Site Plan 6/1/24

 

 

Rendering of New Main Entry (View from Parkhaven) 9/30/24

Rendering of New Main Entry (View from Parkhaven) 9/30/24
 

 

Minor Renovations

Scroll down to view bond major renovation projects:

  • Plano West Senior High School
  • Plano East Senior High School

Plano West Senior High School Building A Renovation

5601 W. Parker Road, Plano, Texas 75093

  • Architect: Glenn Partners 
  • Contractor: Hill & Wilkinson  
  • Plano ISD Construction Administrator: Oscar Mojica 

Scope

Renovation of Building A approximately 145,000 SF including elevator replacement.  Also the removal of 22 operable partition walls in Buildings A and B with solid walls scheduled to be put back in their place.  Campus will also receive an upgrade to the chiller plant and HVAC controls.  About 35,000 SF of addition for two new gym floors, weight room and locker room space.  Campus will also receive updates to safety and security. Site athletic considerations include tennis court replacement/relocation along with storage and restrooms. Baseball and softball dugout extensions.  Auxiliary field LED lights.  Theatrical rigging upgrade in Fine Arts.

Timeline

  • Design Initiated: 7/2023
  • Anticipated Design Completed: 6/2024
  • Expected Construction Started: 8/2024
  • Scheduled Construction Completed: 8/2026

Status

100% Design Development is currently in review.  The architect recently introduced the proposed color palette along with some interior perspectives.  Moving into Construction Documents.   

Estimated Construction Budget

$83,433,722

Conceptual Site Plan Conceptual Site Plan key
Conceptual Site Plan 12/1/23

Conceptual Rendering of New Athletic Entry
Conceptual Rendering of New Athletic Entry 12/1/23


Material & Finish Palette 3/1/24


Rendering of Proposed Main Lobby 3/1/24


Rendering of Proposed Practice Gym 3/1/24

Rendering of Proposed Training Room
Rendering of Proposed Training Room

Rendering of Proposed Locker Room
Rendering of Proposed Locker Room 3/1/24


Plano East Senior High School Building D Renovation

3000 Los Rios Boulevard, Plano, Texas 75074

  • Architect: WRA
  • Contractor: Cadence McShane
  • Plano ISD Construction Administrator: Robert Dean

Scope

Renovation of Building D approximately 7,000 SF.  Ceiling and lights in Buildings B1, B2, B3 and B4.  Upgrade to chiller plant and HVAC controls.  Addition of 35,000 SF for two new gym floors, weight room and some locker room space.  Locker room major renovation.  Site athletic considerations include tennis court replacement/relocation along with storage and restrooms.  Baseball and softball locker rooms with dugout extensions.  Auxiliary field LED lights.  Add restrooms and water to Student Activity Center.  Campus will also receive updates to safety and security.  CTE needs an expanded Consumer Science Lab classroom.  Marching band tower.    

Timeline

  • Design Initiated: 7/2023
  • Anticipated Design Completed: 8/2024
  • Expected Construction Started: 11/2024
  • Scheduled Construction Completed: 11/2026

Status

Design Development is continuing.  Pre-construction meetings with the contractor are occurring to make sure we are still within budget, and to start discussing schedule and how to phase the work.

Estimated Construction Budget

$48,459,610

Conceptual Rendering of Lobby and GymnasiumConceptual Rendering of Lobby and Gymnasium key
Conceptual Rendering of Lobby and Gymnasium 12/1/23

Proposed Additional Gym Floors  Proposed Additional Gym Floors Entrance
Proposed Additional Gym Floors 12/1/23

Proposed Additional Gym InteriorProposed Additional Gym InteriorProposed Additional Gym InteriorProposed Additional Gym Interior

Phase 2

Phase 2

PROJECT

ARCH/ENG
(Board Approved)

CONTRACTOR 

Estimated Construction Budget

Transportation Building Addition/Renovation

 (4/2/24)

TBD 

$14,000,000 (est. budget)

Transportation Fueling Station

(4/2/24)

TBD

1,600,000 (est. budget)

Service Center Renovation

 (4/2/24)

 TBD

$14,500,000 (est. budget)

Frankford Middle School Kitchen Addition/Renovation

 

(4/2/24)

TBD

$6,600,000 (est. budget)

Hightower Elementary School Kitchen Addition/Renovation

(4/2/24)

TBD

$2,400,000 (est. budget)

Systems and Compliance Phase 2
(McMillen, Haun, Bird Center, Clark Stadium, Bethany, Hedgcoxe, Hendrick,Mitchell)

3/19/24

TBD

$8,898,000 (est. budget)

Phase 1

Major Renovations

Scroll down to view bond major renovation projects:


Williams High School Phase 2 Renovation

1818 18th Street, Plano, TX 75074

  • Architect: PBK Architects
  • Contractor: McCown Gordon 
  • Plano ISD Construction Administrator: Quincy Lara

Scope

The first phase of the overall master plan was completed under the 2016 Bond. It included approximately 67,000 square feet of renovation to the Administration, Counseling, SPED, and Art areas. The second phase under the current 2022 Bond will complete the master plan by renovating General Classrooms, CTE, Science, Library, Food Services-Cafeteria, Athletics, and Fine Arts. The Field House will also be renovated including a roof replacement. Site and drainage improvements will also be addressed. The District will take ownership of the Harry Rowlinson Natatorium from the City and will renovate it. 

Timeline

  • Design Initiated: 2/2023
  • Design Completed: 12/2023
  • Expected Construction Started: 3/2024
  • Scheduled Construction Completed: 7/2026

Status

A Change Order was approved in December adding additional scope to the Rowlinson Natatorium which the District took ownership of in January. We will close the natatorium in April to make the necessary renovations, and then look to open it back up in October 2025. 

Current Construction Phases

  • Phases 2, 4, and 5 are ongoing.
  • Phase 1 (Choir, Drama/Theater, new restrooms, and corridor extension) has been completed and turned over to the campus. Minor finishes needed for final completion.
  • Phase 3 (CTE Labs, and additional General Classrooms) are complete and have been turned over to the campus. The AV Lab is currently split, and being used as temporary swing space.

Phase 2

A temporary corridor remains in place to provide the campus with access to the cafeteria and other areas for the remainder of the school year. All steel, exterior walls, and roofing have been completed, above the existing concrete roof slab for the new clerestory area in the proposed main corridor. Ongoing work includes rerouting fire sprinkler lines and steel work below the concrete roof to prepare for the structural slab cuts needed to create the high-volume space.

Phase 4

Construction continues with finalizing ductwork installation, electrical work above the ceiling, rerouting of sprinkler lines, drywall, ceiling installation, and wall finishes. Floor finishes are set to begin soon. Phase 4 is expected to be completed by April 1.

Phase 5

Ongoing demolition and electrical work to ensure safety, plumbing trenches, and rough-in for new lines are underway. Phase 5 is expected to be completed by May, with turnover by August 25. 

Construction Contract Amount

$61,425,507


Plano Senior High School

2200 Independence Parkway, Plano, Texas 75075

  • Architect: Corgan
  • Contractor: CORE
  • Plano ISD Construction Administrator: Quincy Lara

Scope

Renovation of approximately 375,000 SF of existing buildings. Roughly 84,000 SF of Athletic building additions including two new gym floors, new competition gym entry, and rebuilt Student Activity Center. 55,400 SF addition for new Kitchen, Cafeteria and Library. 10,000 SF new front entry. Campus will also receive updates to safety and security. Tennis court relocation along with storage and restrooms, Baseball turf replacement, dugout extensions and locker rooms, new softball field with attached locker rooms. 6’ ornamental fence and gates around existing turf field and track. New LED lights at baseball and softball field.

Timeline

Design Initiated: 7/2023

Package 1 (Baseball/Softball Complex)

  • Design Completion: 4/2024
  • Construction Started: 9/2024
  • Scheduled Construction Completion
    • Fields ready for practice: 2/2025
    • Dugouts/Concession/Tickets: 5/2025

    Package 2 (Remainder of the work)

    • Anticipated Design Completed: 10/2024
    • Expected Construction Started: 3/2025
    • Scheduled Construction Completed: 7/2028

    Status

    Package 1

    Baseball/Softball Complex GMP approved 6/25/24 for $17,091,058. New turf is currently being installed on both fields.

    Package 2

    Remainder of the work was issued for bid in November. A GMP will be recommended to our March Board. Phased construction will start shortly thereafter and will continue through July 2028. 

    Estimated Construction Budget

    $224,300,000 (includes Package 1)


    Early Childhood School Kitchen/Dining Additions

    • Architect: Glenn Partners
    • Contractor: MDI
    • Plano ISD Construction Administrator: Oscar Mojica

    Scope

    Kitchen/Dining room additions at each of the District’s three Early Childhood Schools.

    • Beaty ECS - 1717 Nevada Dr., Plano, Texas 75093
    • Isaacs ECS - 3400 E. Parker Rd., Plano, Texas 75074
    • Pearson ECS - 4000 Eagle Pass, Plano, Texas 75023

    Construction will also include HVAC Controls, new digital marquees, and new chillers at Beaty and Pearson.   

    Timeline

    Design Initiated: 8/2023
    Anticipated Design Completion: 4/2024
    Expected Construction Start: 6/2024
    Scheduled Construction Completion: 9/2025


    Status

    90% Construction Documents.  Initial 50% estimate needed a few clarifications which are anticipated will bring the numbers closer to budget.  Awaiting contractor’s 90% estimate.  Contractor is set to take out for bid with subs mid-April.  Will present a GMP to the Board May 21.     

    Estimated Construction Budget

     Beaty:        $4,961,883
    Isaacs:       $5,884,863
    Pearson:    $5,220,997

    Existing Isaacs Activity Room 12/1/23
    Existing Isaacs Activity Room 12/1/23

    Existing Beaty Dining
    Existing Beaty Dining 12/1/23


    Centennial Elementary School Kitchen Renovation/Addition

    2609 Ventura Drive, Plano, Texas 75093

    • Architect: Stantec
    • Contractor: JC Commercial
    • Plano ISD Construction Administrator: Oscar Mojica

    Scope

    Major remodel of the kitchen, including additional space if needed, including all new equipment.  Systems and compliance items include new electrical panels, fire alarm replacement, new digital marquee, new restroom partitions and some sidewalk repair.  Security recommendations include exterior door position contacts, and additional play area fencing if viable.  Also adding two sinks at the art room.

    Timeline

    • Design Initiated: 8/2023
    • Anticipated Design Completed: 2/2024
    • Expected Construction Started: 4/2024
    • Scheduled Construction Completed: 11/2024

    Status

    Opened bids February 13th from four bidders.  Evaluation team reviewed bids and recommended JC Commercial.  Anticipate starting construction in April.

    Estimated Construction Budget

    $3,062,777


    Clark High School Structural Repair/Renovation

    523 Spring Creek Parkway, Plano, Texas 75023

    • Architect: Corgan
    • Contractor: TBD (CSP)
    • Plano ISD Construction Administrator: Quincy Lara

    Scope

    Structural repairs of the special education area, two interior stairs, some sidewalks and a ramp along the east side of the building.  Also will look to replace the slabs and floors in both gyms.  In replacing the gym floors there is also the opportunity to follow athletic realignment.  Systems and compliance items include new controls, new cooling tower and some new RTUs.  Security recommendations include entry resistant film at main and secondary entries, emergency call stations, additional parking lot lighting, exterior door position contacts, and additional cameras.

    Timeline

    • Design Initiated: 8/2023
    • Anticipated Design Completed: 8/2024
    • Expected Construction Started: 10/2024
    • Scheduled Construction Completed: 8/2025

    Status

    Corgan walked the site with consultants to inspect the existing conditions back in late February.  Still anticipate issuing bid documents the end of summer of 2024.  The contractor will procure materials in the winter and spring with construction being completed over the summer of 2025.

    Estimated Construction Budget

    $3,738,508


    Haggard Middle School Replacement

    2832 Parkhaven Drive, Plano, Texas 75075

    • Architect: VLK
    • Contractor: CORE
    • Plano ISD Construction Administrator: Quincy Lara

    Scope

    Construction of a new Haggard Middle School (Grades 6-8) approximately 187,900 SF.  It will be built on the existing site to replace the current campus. The existing building will remain in use during the construction of the project, and great care will be given to protect and maintain the present site, building, services, infrastructure, security and access.  Once the new building is complete the existing will be demolished.  Site conditions such as circulation drives, fire lanes, parking, and landscape/irrigation will be included in the work and overall plan along with a new 4-lane synthetic track. 

    Timeline

    • Design Initiated: 7/2023
    • Anticipated Design Completed: 11/2024
    • Expected Construction Started: 3/2025
    • Scheduled Construction Completed:
      • New Building, paving and drives: 8/2026
      • Demo of the existing building, and building of new Track: 2/2027

    Status

    The project was issued for bid in November. Sub bids were collected in December with the following weeks spent evaluating, scoping and making selections. A GMP (Guaranteed Max Price) was submitted in January, and will be reviewed by the Board for approval February 4, 2025. With Board approval, and pending final permit release from the City, construction is expected to start shortly thereafter. The contractor is expecting an NTP (Notice To Proceed) 2/7/25 with an 18 month construction duration for the new building.

    Estimated Construction Budget

    $86,612,925

CTE and Innovative Programs

Scroll down to view bond CTE and Innovative Programs projects:

  • Career and Technical Education Center

Career and Technical Education Center

1865 Alma Drive, Plano, TX 75075

  • Architect: Huckabee
  • Contractor: Joeris
  • Plano ISD Construction Administrator: Robert Dean

Scope

Construction of a new Career and Technical Education Center approximately 159,463 SF. The Career and Technical Education (CTE) Center will offer students the academic and relevant technical skills, knowledge and training necessary to prepare for further education and careers in current or emerging professions. The center will be a state-of-the-art facility with real-world learning spaces, and equipment for students 9th-12th. Circulation, fire lanes, parking, and landscape/irrigation will be examined and included in the work and overall plan. 

Timeline

  • Design Initiated: 7/2023
  • Anticipated Design Completion: 8/2024
  • Expected Construction Start: 2/2025
  • Scheduled Construction Completion: 10/2026

Status

In November the GMP was approved by the Board, and the City Council approved the preliminary site plan and re-zoning which allowed plans to be submitted for permit. Recently City Engineering sent a checklist of items needed to pull out three separate permits which would allow the contractor to begin in a way that would allow continuous construction. A grading, utilities, and foundation permit. It is anticipated the early grading permit will be released no later than this month (January) upon which the contractor can start clearing/grubbing of the site. After which time actual heavy earthwork would begin. The contractor continues buy out the project. 

Construction Contract Amount 

$75,128,866

Maintaining Our Infrastructure

Scroll down to view bond infrastructure construction projects:

  • Jupiter Center Renovation
  • Murphy Distribution Center Addition

Jupiter Center Renovation

2450 Jupiter Road, Plano Texas 75074

  • Architect: PBK
  • Contractor: McCown Gordon
  • Plano ISD Construction Administrator: Quincy Lara

Scope

The demolition of about 3,000 SF of interior office space, and the building back of approximately 7,000 SF of new interior office for Technology Deployment and Learning Media Services.  The existing facade will be updated to create a new entry point.  Site work includes new site fencing, motorized gates, and site lighting.  In addition, the existing roof will be replaced with a new roof system. 

Timeline

  • Design Initiated: 8/2022
  • Design Completed: 2/2023
  • Construction Start: 3/2023
  • Scheduled Construction Completion: 2/2025

Status

Substantially complete.  The staff moved in June of 2024, and are currently occupying the space. Punch list items are ongoing. Change Order 1 was approved in September of 2024 to address replacing the front asphalt parking lot.  The contractor is expected to start laying new asphalt 1/23/2025. After replacing the asphalt parking, the contractor will install the fencing and finish the landscape to complete the project.

Construction Contract Amount

$2,946,000 

Existing Asphalt Parking Lot - 8/1/2024

Existing Asphalt Parking Lot - 8/1/2024

Interior View of Warehouse - 8/1/2024

Interior View of Warehouse - 8/1/2024

Asphalt Work Starting - 1/23/2025

Asphalt Work Starting - 1/23/2025


Murphy Distribution Center Addition

650 N. Murphy Road, Murphy, Texas 75094

  • Architect: PBK
  • Contractor: Taurus Commercial
  • Plano ISD Construction Administrator: Quincy Lara

Scope

The addition of approximately 15,900 SF of warehouse storage to the existing Murphy Distribution Center.  Work includes a new loading dock ramp, minor fencing modifications, and associated site work.  The addition also includes room for JROTC.          

Timeline

  • Design Initiated: 8/2022
  • Design Completed: 2/2023
  • Construction Started: 3/2023
  • Construction Completed: 6/2024

Status

Substantially Complete.  Moved into new warehouse back in June.  Punch list items are ongoing. 

Construction Contract Amount

$3,545,114 

Final Contract Price

$3,387,365 

Exterior View of Addition - 8/1/2024

Exterior View of Warehouse Addition - 8/1/2024

Interior View of Addition - 8/1/2024

Interior View of Warehouse Addition - 8/1/2024


Enhancements - Campus Athletics - Phase 1

Scroll down to see bond athletics enhancements:

  • Plano East and West Track Fencing
  • Plano East Baseball & Softball Turf
  • Plano West Baseball & Softball Turf

Plano East and West Track Fencing

  • Engineer: RLK
  • Contractor: Robinson Fence Company
  • Plano ISD Construction Administrator: Robert Dean

Scope

Removal of existing 4’ chain link fence, fence posts, mow strip, and gates, and installation of new 6’ ornamental fence, fence posts, gates, and mow strip around the perimeter of the competition running tracks and turf football fields at Plano East Senior High School and Plano West Senior High School.

Timeline

  • Design Initiated: 3/2023
  • Design Completed: 6/2023
  • Construction Started: 7/2023
  • Construction Completed: 12/2023

Status

Complete. 

Construction Contract Amount

Plano East: $255,550
Plano West: $278,750

Final Contract Price

Plano East: $244,057
Plano West: $273,689


Plano East Baseball & Softball Turf

3000 Los Rios Blvd., Plano, Texas 75074

  • Engineer: RLK
  • Contractor: Hellas 
  • Plano ISD Construction Administrator: Robert Dean

Scope

Provide new synthetic turf at both the baseball and softball fields.   The existing baseball currently has turf in the infield, and grass in the outfield.  The existing softball has dirt in the infield, and turf in the outfield.  This project will look to install new turf on the entirety of both fields (infields and outfields alike).  A Change Order approved in October added a metal outfield fence for baseball.

Timeline

  • Design Initiated: 5/2023
  • Design Completed: 8/2023
  • Construction Started: 9/2023
  • Construction Completed: 1/2024

Status

Substantially complete.  Punch list completed.  Working through As-builts and Closeout Documents

Construction Contract Amount

$2,870,477


Plano West Baseball & Softball Turf

5601 W. Parker Road, Plano, Texas 75093

  • Engineer: RLK
  • Contractor: Paragon
  • Plano ISD Construction Administrator: Robert Dean

Scope

Provide new synthetic turf at both the baseball and softball fields.   The existing baseball currently has turf in the infield, and grass in the outfield.  The existing softball has dirt in the infield, and turf in the outfield.  This project will look to install new turf on the entirety of both fields (infields and outfields alike).  A Change Order approved in October added a metal outfield fence for softball.     

Timeline

  • Design Initiated: 5/2023
  • Design Completed: 8/2023
  • Construction Started: 9/2023
  • Construction Completed: 1/2024

Status

Complete. 

Construction Contract Amount

$2,827,125

Final Contract Price

$2,801,193

Enhancements - Middle School Tracks - Phase 1

Scroll down to see bond middle school track projects:

  • Bowman MS
  • Robinson MS
  • Wilson MS

Bowman MS Synthetic Track 

2501 Jupiter Road, Plano, Texas 75074

  • Engineer: RLK
  • Contractor: Hellas
  • Plano ISD Construction Administrator: Robert Dean

Scope

Provide new, all weather, synthetic track.  300m 4-lane track  with natural grass infield.         

Timeline

  • Design Initiated: 3/2023
  • Design Completed: 8/2023
  • Construction Started: 11/2023
  • Construction Completed: 4/2024

Status

Substantially complete.

Construction Contract Amount

$1,484,465


Robinson MS Synthetic Track 

6701 Preston Meadow Drive, Plano, Texas 75024

  • Engineer: RLK
  • Contractor: Hellas
  • Plano ISD Construction Administrator: Robert Dean

Scope

Provide new, all weather, synthetic track.  300m 4-lane track  with natural grass infield.         

Timeline

  • Design Initiated: 3/2023
  • Design Completed: 8/2023
  • Construction Started: 11/2023
  • Construction Completed: 8/2024

Status

Substantially complete.

Construction Contract Amount

$2,182,675


Wilson MS Synthetic Track 

1001 Custer Road, Plano, Texas 75075

  • Engineer: RLK
  • Contractor: Hellas
  • Plano ISD Construction Administrator: Robert Dean

Scope

Provide new, all weather, synthetic track.  300m 4-lane track  with natural grass infield.         

Timeline

  • Design Initiated: 3/2023
  • Design Completed: 8/2023
  • Construction Started: 11/2023
  • Construction Completed: 8/2024

Status

Substantially complete.

Construction Contract Amount

$1,878,485


Enhancements - Safety and Security

Scroll down to view bond safety and security enhancements:

  • Classroom Doors & Entry Resistant Film

Classroom Doors & Entry Resistant Film 

(Elementary Schools, Early Childhood Schools, Early Childcare Centers)

  • Architect: WRA
  • Contractor: Gliden Industries
  • Plano ISD Construction Administrator: Robert Dean/Quincy Lara

Scope

Add classroom doors to all elementary school classrooms currently without a door.  Add entry resistant film on main vestibules, secondary entries and all windows. Modify all existing classroom door hardware to storeroom function.  The project covers 44 elementary schools and includes the installation of about 730 doors, and 126,000 SF of film.  A change order in June added scope to the project to include entry resistant film at our three early childhood schools and two early childcare centers.

Timeline

  • Design Initiated: 3/2023
  • Design Completed: 5/2023
  • Construction Started: 62023
  • Construction Completed: 9/2024

Status

Substantially complete November of 2023 with all elementary school campuses.  Change Order 1 was approved June of 2023 and added the early childhood schools, and early childcare centers to the project.  The three early childhood schools, and two of the three early childcare centers were also completed by November of 2023.  However, at the Pebble Creek Early Childcare Center it was found the existing window frames and doors were residential, and would need to be replaced in order to accept the film.  Architectural details needed to be developed, and the doors and windows could not be replaced while school was in session.  So this work began June of 2024, and was substantially complete by September of 2024.  

Construction Contract Amount

$7,073,030

Playgrounds

Playgrounds - Phase 1

Scroll down to view ADA playgrounds projects:

  • Aldridge ES
  • Barksdale ES
  • Bethany ES
  • Boggess ES
  • Brinker ES
  • Carlisle ES
  • Hughston ES
  • Meadows ES
  • Stinson ES

Aldridge ES Playground Replacement 

  • Engineer: CEI
  • Contractor: Innovative Sport Surfacing 
  • Plano ISD Construction Administrator: Robert Dean

Scope

Provide new, all weather, ADA accessible, upper unit playground with sunshade canopy.

Timeline

  • Design Initiated: 3/2023
  • Anticipated Design Completed: 6/2023
  • Expected Construction Start: 9/2023
  • Scheduled Construction Completion 7/2024

Status

Substantially complete 

Estimated Construction Budget

$311,985


Barksdale ES Playground Replacement 

  • Engineer: RLK
  • Contractor: We Build Fun
  • Plano ISD Construction Administrator: Robert Dean

Scope

Provide new, all weather, ADA accessible, lower and upper unit playgrounds with sunshade canopy.

Timeline

  • Design Initiated: 3/2023
  • Anticipated Design Completed: 8/2023
  • Expected Construction Start: 11/2023
  • Scheduled Construction Completion 7/2024

Status

Substantially complete 

Estimated Construction Budget

$599,990


Bethany ES Playground Replacement 

  • Engineer: RLK
  • Contractor: We Build Fun
  • Plano ISD Construction Administrator: Robert Dean

Scope

Provide new, all weather, ADA accessible, lower and upper unit playgrounds with sunshade canopy.

Timeline

  • Design Initiated: 3/2023
  • Anticipated Design Completed: 8/2023
  • Expected Construction Start: 11/2023
  • Scheduled Construction Completion 7/2024

Status

Substantially complete 

Estimated Construction Budget

$599,990


Beverly ES Playground Replacement

715 Duchess Dr, Allen, TX 75013

  • Engineer: RLK
  • Contractor: We Build Fun 
  • Plano ISD Construction Administrator: Robert Dean

Scope

Provide new, all weather, ADA accessible, lower and upper unit playgrounds with sunshade canopy.

Timeline

  • Design Initiated: 3/2023
  • Anticipated Design Completed: 8/2023
  • Expected Construction Start: 9/2024
  • Scheduled Construction Completion
    • Upper Playground: 12/2024
    • Lower Playground: 3/2025

Status

Upper unit playground curbs installed. Playground equipment is complete. Shade structure is complete. Turf Installation began early December. Irrigation repair/ installation complete. Prepping for sod installation expecting to turn over upper playground upon students return after Winter Break. Then they will move efforts to the lower playground replacement.

Estimated Construction Budget

$689,466


Bogges ES Playground Replacement 

225 Glen Ridge Drive, Murphy, TX 75094 

  • Engineer: RLK
  • Contractor: We Build Fun 
  • Plano ISD Construction Administrator: Robert Dean

Scope

Provide new, all weather, ADA accessible, lower and upper unit playgrounds with sunshade canopy.

Timeline

  • Design Initiated: 3/2023
  • Anticipated Design Completed: 8/2023
  • Expected Construction Start: 9/2024
  • Scheduled Construction Completion
    • Upper Playground: 12/2024
    • Lower Playground: 3/2025

Status

Upper unit playground is 98% complete and lower unit to begin in February.

Estimated Construction Budget

$599,99


Brinker ES Playground Replacement 

3800 John Clark Parkway, Plano, Texas 75093

  • Engineer: RLK
  • Contractor: We Build Fun
  • Plano ISD Construction Administrator: Robert Dean

Scope

Provide new, all weather, ADA accessible, lower and upper unit playgrounds with sunshade canopy.

Timeline

  • Design Initiated: 3/2023
  • Anticipated Design Completed: 8/2023
  • Expected Construction Start: 11/2023
  • Scheduled Construction Completion 7/2024

Status

Substantially complete 

Estimated Construction Budget

$599,990


Carlisle ES Playground Replacement 

6525 Old Orchard Drive, Plano, Texas 75023

  • Engineer: RLK
  • Contractor: We Build Fun
  • Plano ISD Construction Administrator: Robert Dean

Scope

Provide new, all weather, ADA accessible, lower and upper unit playgrounds with sunshade canopy.

Timeline

  • Design Initiated: 3/2023
  • Anticipated Design Completed: 8/2023
  • Expected Construction Start: 11/2023
  • Scheduled Construction Completion 7/2024

Status

Substantially complete 

Estimated Construction Budget

$628,638


Hughston ES Playground Replacement 

    • Engineer: RLK
    • Contractor: We Build Fun
    • Plano ISD Construction Administrator: Robert Dean

    Scope

    Provide new, all weather, ADA accessible, lower and upper unit playgrounds with sunshade canopy.

    Timeline

    • Design Initiated: 3/2023
    • Anticipated Design Completed: 8/2023
    • Expected Construction Start: 11/2023
    • Scheduled Construction Completion 7/2024

    Status

    Substantially complete 

    Estimated Construction Budget

    $599,990


    Meadows ES Playground Replacement 

    2800 18th Street, Plano, Texas 75074

    • Engineer: RLK
    • Contractor: We Build Fun
    • Plano ISD Construction Administrator: Robert Dean

    Scope

    Provide new, all weather, ADA accessible, lower and upper unit playgrounds with sunshade canopy.

    Timeline

    • Design Initiated: 3/2023
    • Anticipated Design Completed: 8/2023
    • Expected Construction Start: 11/2023
    • Scheduled Construction Completion 7/2024

    Status

    Substantially complete 

    Estimated Construction Budget

    $602,392


    Stinson ES Playground Replacement 

    • Engineer: CEI
    • Contractor: Innovative Sport Surfacing 
    • Plano ISD Construction Administrator: Robert Dean

    Scope

    Provide new, all weather, ADA accessible, upper unit playground with sunshade canopy.

    Timeline

    • Design Initiated: 3/2023
    • Anticipated Design Completed: 6/2023
    • Expected Construction Start: 9/2023
    • Scheduled Construction Completion 7/2024

    Status

    Substantially complete 

    Estimated Construction Budget

    $311,985



Systems and Compliance

Systems & Compliance

Scroll down to view bond systems and compliance projects:

  • McMillen HS Systems & Compliance
  • Bird Center
  • Clark Stadium

McMillen HS Systems & Compliance

750 N. Murphy Road, Murphy, Texas 75094

  • Architect: Estes McClure
  • Contractor: Infinity
  • Plano ISD Construction Administrator: Oscar Mojica

Scope

The project involves upgrading the campus with modern lighting controls and new energy-efficient lighting fixtures across all areas. Additionally, it includes replacing the HVAC control systems throughout the campus with updated, efficient solutions.

Timeline

  • Design Initiated: 3/2023
  • Design Completed: 8/2023
  • Construction Start: 12/2024
  • Scheduled Construction Completion: 8/2025

Status

The contractor mobilized on December 20, 2024 and began the demolition of existing lighting and the installation of new LED fixtures. Enviromatics successfully completed the CAT6 control wiring throughout the building during this phase.

Construction Contract Amount

$4,395,849 


Bird Center Systems & Compliance

1300 19th Street, Plano, Texas 75074

  • Architect: Estes McClure
  • Contractor: ACIS
  • Plano ISD Construction Administrator: Oscar Mojica

Scope

Controls, chiller replacements and security upgrades.

Timeline

  • Design Initiated: 3/2024
  • Design Completed: 7/2024
  • Construction Start: 3/2025
  • Scheduled Construction Completion: 8/2025

Status

Contractor approved in August 2024.  Reviewing submittals.  Begin pulling cable for new controls starting Spring Break 2025.

Construction Contract Amount

$1,234,257 


Clark Stadium Systems & Compliance

6600 Stadium Drive, Plano, Texas 75023

  • Architect: Estes McClure
  • Contractor: ACIS
  • Plano ISD Construction Administrator: Oscar Mojica

Scope

Controls, chiller replacements and security upgrades.

Timeline

  • Design Initiated: 3/2024
  • Design Completed: 7/2024
  • Construction Start: 3/2025
  • Scheduled Construction Completion: 8/2025

Status

Contractor approved in August 2024.  Reviewing submittals.  Begin pulling cable for new controls starting Spring Break 2025.

Construction Contract Amount

$1,234,257