• 2016 Bond Quarterly Construction Update

    January - March 2023

    Our Planning and Construction Department reports the progress of construction and renovation projects on a quarterly basis. 

     Bowman MS renovation

Administration

    • Deputy Superintendent for Business & Employee Services, Johnny Hill

Facility Planning and Construction

    • Executive Director of Facility Services, Juan Ramos
    • Assistant Director of Facility Services, Tony Pearson
    • Construction Manager, Johnny Pechacek
    • Construction Administrator, Robert Dean
    • Construction Administrator, Warren Kinsey
    • Construction Administrator, Quincy Lara
  • New Construction

    Scroll down to view bond new construction projects:

    • Robbie & Lynore Robinson Fine Arts Center
    • Early Childhood School 4
    • Wraparound Services Center
    • Clark JV Field Locker Room

    Robbie & Lynore Robinson Fine Arts Center

    1800 Alma Drive, Plano, TX 75075

    • Architect: P+W/BORA
    • Contractor: McCarthy
    • Plano ISD Construction Administrator: Johnny Pechacek, Warren Kinsey

    Scope

    Provide a venue to showcase music, dance, theater and the visual arts. The facility will be approximately 82,200 SF spread across two levels. The main theater will have 1,500 seats and one balcony level. The building will also have a flexible 200 seat Studio Theater, large Rehearsal Room and Gallery component for exhibitions. Designed to host art contests, including University Interscholastic League (UIL) competitions with schools from outside of the district. The facility also has the potential to host outside performances and events, bringing art and culture from a variety of sources into the community of Plano.

    Timeline

    • Design Initiated: 2/2017
    • Design Completed: 6/2018
    • Construction Started: 1/2019
    • Scheduled Construction Completion: TBD
    • Construction Substantially Completed: 12/2022
    • Floor Remediation Completed: 12/2022
    • Exterior Wall Remediation Completed: TBD

    Status

    Substantially Complete

    The grand opening of the Robbie & Lynore Robinson Fine Arts Center, originally scheduled for mid January, has been postponed. As construction has progressed, the floors in the building show evidence of significant cracking as a result of poor workmanship and/or design that do not meet the aesthetic standards established by Plano ISD. Mindful of our obligation to students, parents, staff, the taxpayers and the many supporters of this facility, Plano ISD leaders have elected not to take occupancy of the facility until this deficiency is resolved to the satisfaction of the District. 

    Understanding the ripple effect this has on our district and community, we will announce a new grand opening date as soon as we are able. Plano ISD students deserve a facility that honors their commitment to the arts and our goal is to make sure that you, our district and our community can be proud of our new home for the arts in Plano ISD.

    Remediation

    Floor remediation was completed in December.  The District began to take over the building in late January, changing the locks, deep cleaning all areas, and moving in furniture.  Mid to late March the Fine Arts Department started using the space for small UIL events and youth art month exhibits for elementary and secondary.  A Grand Opening is anticipated for May.

    The exterior wall remediation is still underway, and expected to be completed mid-April.  A majority of the exterior has been painted with the elastomeric in a two tone color scheme proposed by the architect.

    CONSTRUCTION CONTRACT AMOUNT

    $54,015,932 

    Exterior Elastomeric Paint March 2023
    Exterior Elastomeric Paint - March 2023

    Art Gallery March 2023
    Art Gallery - March 2023


    Early Childhood School 4

    Mapleshade Lane, Dallas, TX 75252

    • Architect: VLK Architects
    • Contractor: Cadence McShane
    • Plano ISD Construction Administrator: Warren Kinsey

    Scope

    Enlarge the capacity of the district's Early Childhood Program by constructing a fourth campus. The new school will be modeled after the Sara Isaacs Early Childhood School, but will also contain a kitchen and dining area. The building will be approximately 62,500 SF. Site conditions such as circulation, fire lanes, parking, landscape and irrigation will also be included in the work and overall planning.

    Timeline

    • Design Initiated: 6/2017
    • Design Completed: 4/2018
    • Voted Down By Board: 6/2018

    Status

    The Board requested further study on the district’s immediate need for a fourth early childhood school. To be brought forward at a subsequent time.  Contracts with both the contractor and the architect have been closed.

    The Wraparound Services Center is now scheduled to be built on this site. 

    Early Childhood School 4 floor plan

    Overall floor plan, June 2018

    Early Childhood School Main Entry Rendering

    Main entry rendering, June 2018


    Wraparound Services Center

    Mapleshade Lane, Dallas, TX 75252

    • Architect: VLK Architects
    • Contractor: JC Commercial
    • Plano ISD Construction Administrator: Robert Dean

    Scope

    Build a new, approximately 11,000 SF, facility to help serve the District in regards to Counseling and Academic Planning, Student Services, Community and Social Services, Family Engagement, and Health and Wellness.  Site conditions such as traffic, fire lanes, parking, landscape and irrigation will also be included in the work and overall planning.

    Timeline

    • Design Initiated: 4/2021
    • Scheduled Design Completion: 1/2022
    • Scheduled Permit Release: TBD
    • Scheduled Construction Start: TBD
    • Scheduled Construction Completion: 365 days after permit

    Status

    JC Commercial was recommended, and approved at the 1/10/23 Board.  The plans are currently with the City of Dallas awaiting the release of permit.  Once released the contractor will start mobilizing on site.  In the meantime they have started submittals, and buying out subcontracts. 

    Estimated Construction Amount

    $5,550,777

    Site view, NW corner

    View of site from NW corner, September 2021

    Site plan Sept 2021

    Site plan, September 2021

    Exterior rendering Dec 2021
    Exterior Rendering, December 2021


    Clark JV Locker Room

    6600 Stadium Drive, Plano, TX 75023

    • Architect: VLK Architects
    • Contractor: ICI
    • Plano ISD Construction Administrator: Robert Dean

    Scope

    The new masonry unit building is comprised of two separate athletic locker rooms, and one locker room for officials.  New construction will include heating only, lighting and minimal electrical convenience power outlets.

    Timeline

    • Design Initiated: 6/2017
    • Design Completed: 4/2018
    • Construction Start: 3/2021
    • Scheduled Construction Completion: 11/2021
    • Construction Completed: 3/2022

    Status

    Complete

    Estimated Construction Amount

    $718,000

    Actual Construction Cost

    $714,422.10

    ClarkJV locker

    New JV Fields Locker Room, March 2022

    Clark JV locker room

    Interior View of Locker Room, March 2022

  • New Acquisitions

    Scroll down to view new bond acquisition projects:

    • Charmaine Solomon Adult Transition Center
    • Employee Childcare 3

    Charmaine Solomon Adult Transition Center

    1631 Dorchester Dr., Plano, TX 75075

    • Architect: PBK Architects
    • Contractor: District Approved Vendors
    • Plano ISD Construction Administrator: Warren Kinsey

    Scope

    • Phase 1 - Interior finish-out and building infrastructure upgrades to provide one center for all Special Education Transition Services for the District.  Transition services are a coordinated set of activities designed as a results oriented process that promotes movement from school to post-school activities, including: post-secondary education, vocational training, integrated employment (including supported employment), continuing and adult education, adult services, independent living, or community participation.
    • Phase 2 – Minor renovation of the kitchen and replacement of select kitchen equipment.

    Timeline

    • Building Purchased: 4/2017
    • Previous Owner Moved Out: 5/2018
    • Phase 1
      • Construction Started: 6/2018
      • Construction Completed: 8/2018
    • Phase 2
      • Construction Started: 6/2021
      • Construction Completed: 8/2021

    Status

    Complete. 

    Construction Contract Amount:

    • Phase 1: $700,000
    • Phase 2: $510,850

    Actual Construction Cost:

    • Phase 1: $700,000
    • Phase 2: $486,109.80

    New Monument Sign

    New monument sign, December 2019

    Existing Kitchen, September 2020  Existing Kitchen, September 2020

    Existing Kitchen, September 2020

    Drywall Installation

    Drywall Installation, June 2021

    Underground Plumbing

    Underground Plumbing, June 2021


    Employee Child Care 3

    600 Old Custer Rd., Allen, TX 75013

    • Contractor: District Approved Vendors
    • Plano ISD Central Cluster Manager: Jason Wink

    Scope

    Renovate the recently purchased Montessori school and turn it into an  Employee Child Care Center.  Child Care Centers are licensed through the Texas Department of Family and Protective Services.  The District’s Employee Child Care was created to provide a service for our teachers. The exceptional centers have proven to be a valuable tool in the retention and recruitment of the very best teachers in North Texas. This will be the District’s third employee child care.

    Timeline

    • Building Purchased: 8/2017
    • Building Licensed: 6/2018
    • Building Opened: 8/2018

    Status

    Complete.

    Actual Construction Cost

    $4,546,199

    Interior Rooms Under Construction_June2018

    Interior rooms under construction, June 2018

    Classroom View_March2019

    Classroom view, March 2019

  • Added Capacity

    Scroll down to view bond added capacity project for Gulledge Elementary.


    Gulledge Elementary School

    6801 Preston Meadow Drive, Plano, TX 75024

    • Architect: WRA Architects
    • Contractor: Lee Lewis Construction
    • Plano ISD Construction Administrator: Quincy Lara

    Scope

    Provide a six classroom addition, along with associated site-work and paving.

    Timeline

    • Design Initiated: 6/2019
    • Design Completion: 11/2019
    • Construction Start: 3/2020
    • Construction Completed: 10/2020

    Status

    Substantially Complete. Closeout documents being gathered.

    Construction Contract Amount

    $4,209,999

    Actual Construction Cost

    $4,049,571.94

    New Classroom Hallway, September 2020

    New Classroom Hallway, September 2020

    Classroom Addition, December 2020

    Classroom Addition, December 2020

    Classroom Addition, December 2020  Classroom Addition, December 2020

    Classroom Addition, December 2020

  • Major Renovations

    Scroll down to view bond major renovation projects:

    • Robinson Middle School
    • Shepton High School

    Robinson Middle School

    6701 Preston Meadow Dr, Plano, TX 75024

    • Architect: Corgan
    • Contractor: Cadence McShane
    • Plano ISD Construction Administrator: Robert Dean

    Scope

    Provide a major renovation of the existing campus. The design includes approximately 17,900 square feet of addition, and renovation of most of the school’s existing floor plan. The renovation looks to enlarge undersized classrooms, improve interior building circulation, remodel the kitchen, provide new finishes (flooring, paint and tile) throughout, improve upon the athletic locker room spaces, address major building systems (electrical, mechanical, plumbing), and install a new roof. It will also be the second school in the district to go geothermal.

    Timeline

    • Design Initiated: 3/2017
    • Design Completed: 2/2018
    • Construction Started: 3/2018
    • Construction Completed: 8/2019

    Status

    Complete.

    Construction Contract Amount

    $27,971,729

    Actual Construction Cost

    $28,683,894.41
    Additional funds were added for skylights, which were fully covered by insurance, and for fireproofing added per the City of Plano plan review comments.

    Remodeled kitchen

    Remodeled kitchen, October 2019

    Renovated science lab

    Renovated science lab, October 2019


    Shepton High School

    5505 Plano Parkway, Plano, TX 75093

    • Architect: VLK Architects
    • Contractor: Pogue Construction
    • Plano ISD Construction Administrator: Robert Dean

    Scope

    Provide a major renovation of the existing campus. The design consists of approximately 28,000 square feet of addition, and renovation of most of the school’s existing floor plan. The renovation looks to enlarge undersized classrooms, improve interior building circulation, remodel and expand the kitchen, enclose the cafetorium and acoustically treat it for performances, provide new finishes (flooring, paint and tile) throughout, improve upon the athletic locker room spaces, address major building systems (electrical, mechanical, plumbing), install a new roof, and improve the site drive lanes. 

    Timeline

    • Design Initiated: 5/2016
    • Design Completed: 3/2017
    • Construction Started: 4/2017
    • Construction Completed: 8/2018

    Status

    Complete.

    Construction Contract Amount

    $36,471,849

    Actual Construction Cost

    $36,471,849

    Shepton entrance stairs

    Shepton High School entry, July 2019, photo credit: Chad Davis Photography

    Shepton collaboration space

    Collaboration space, photo credit: Chad Davis Photography

    Shepton commons area

    Student commons, July 2019

  • Upgrades/Refurbishments - Elementary Schools

    Scroll down to see the following elementary school bond upgrade/refurbishment projects:

    • Barksdale Elementary School
    • Gulledge Elementary School
    • Haggar Elementary School
    • Haun Elementary School
    • Miller Elementary School
    • Skaggs Elementary School

    Barksdale Elementary School

    2424 Midway Road, Plano, TX 75093

    • Architect: BLC Architecture
    • Contractor: Starling Richardson
    • Plano ISD Construction Administrator: Warren Kinsey

    Scope

    Provide a refurbishment and overall renewal of the existing school. The building will receive all new finishes throughout including paint, carpet and tile. Also new casework, new metal lockers, new ceiling tile and grid. The existing kitchen also receives a complete remodel with all new equipment. Two classrooms are also being added.

    Timeline

    • Design Initiated: 6/2017
    • Design Completed: 2/2018
    • Construction Started: 3/2018
    • Construction Completed (Summer Refurbishment): 8/2018
    • Kitchen and CR Addition Completed: 2/2019

    Status

    Complete.

    Construction Contract Amount

    $6,829,000

    Actual Construction Cost

    $6,744,824.71

    Main Hall, September 2018

    Main hall, September 2018

    Library

    Library, March 2019


    Gulledge Elementary School

    6801 Preston Meadow Drive, Plano, TX 75024

    • Architect: WRA Architects
    • Contractor: Starling Richardson
    • Plano ISD Construction Administrator: Quincy Lara

    Scope

    Provide a refurbishment and overall renewal of the existing school. The building will receive all new finishes throughout including paint, carpet and tile. Also new casework, new metal lockers, new ceiling tile and grid. The existing kitchen also receives a complete remodel with all new equipment.

    Timeline

    • Design Initiated: 5/2016
    • Design Completed: 10/2016
    • Construction Started: 3/2017
    • Construction Completed: 8/2017
    • Kitchen Remodel Completed: 10/2017
    • New Chillers Completed: 8/2018

    Status

    Complete. Project funds allowed for two new chillers to be added to the original scope of work.

    Construction Contract Amount

    $5,607,236

    Actual Construction Cost

    $5,636.290.70

    Refurbished hallway

    Refurbished hallway, June 2017

    new soils separator

    New soils separator, September 2018


    Haggar Elementary School

    17820 Campbell Road, Dallas, TX 75252

    • Architect: WRA Architects
    • Contractor: Starling Richardson
    • Plano ISD Construction Administrator: Warren Kinsey

    Scope

    Provide a refurbishment and overall renewal of the existing school. The building will receive all new finishes throughout including paint, carpet and tile. Also new casework, new metal lockers, new ceiling tile and grid. The existing kitchen also receives a complete remodel with all new equipment.

    Timeline

    • Design Initiated: 5/2016
    • Design Completed: 10/2016
    • Construction Started: 3/2017
    • Construction Completed: 8/2017

    Status

    Complete.

    Construction Contract Amount

    $5,876,489

    Actual Construction Cost

    $5,528,189.06

    Refurbished Hallway

    Refurbished hallway, October 2017

    Refurbished Classroom Pod, October 2017

    Refurbished classroom pod, October 2017


    Haun Elementary School

    4500 Quincy Lane, Plano, TX 75024

    • Architect BLC Architecture
    • Contractor: Bartlett Cocke
    • Plano ISD Construction Administrator: Warren Kinsey

    Scope

    Provide a refurbishment and overall renewal of the existing school. The building will receive all new finishes throughout including paint, carpet and tile. Also new casework, new metal lockers, new ceiling tile and grid. The existing kitchen also receives a complete remodel with all new equipment.

    Timeline

    • Design Initiated: 5/2018
    • Design Completed: 11/2018
    • Construction Started: 3/2019
    • Construction Completed: 8/2019

    Status

    Complete

    Actual Construction Cost

    $7,313,358.25

    Main hallway

    Main street, December 2019

    Dining area

    Dining, December 2019


    Miller Elementary School

    5651 Coventry, Richardson, TX 75082

    • Architect: BLC Architecture
    • Contractor: Starling Richardson
    • Plano ISD Construction Administrator: Warren Kinsey

    Scope

    Provide a refurbishment and overall renewal of the existing school. The building will receive all new finishes throughout including paint, carpet and tile. Also new casework, new metal lockers, new ceiling tile and grid. The existing kitchen also receives a complete remodel with all new equipment.

    Timeline

    • Design Initiated: 6/2017
    • Design Completed: 2/2018
    • Construction Started: 3/2018
    • Construction Completed: 8/2018

    Status

    Complete.

    Construction Contract Amount

    $5,989,000

    Actual Construction Cost

    $5,895,024.95

    Main hall

    Main hall, March 2019

    Library

    Library, March 2019


    Skaggs Elementary School

    3201 Russell Creek Drive, Plano, TX 75025

    • Architect: BLC Architecture
    • Contractor: Bartlett Cocke
    • Plano ISD Construction Administrator: Warren Kinsey

    Scope

    Provide a refurbishment and overall renewal of the existing school. The building will receive all new finishes throughout including paint, carpet and tile. Also new casework, new metal lockers, new ceiling tile and grid. The existing kitchen also receives a complete remodel with all new equipment.

    Timeline

    • Design Initiated: 5/2018
    • Design Completed: 11/2018
    • Construction Started: 3/2019
    • Construction Completed (Summer Refurbishment): 8/2019
    • Kitchen Completed: 12/2019

    Status

    Complete

    Construction Contract Amount

    $6,632,771

    Actual Construction Cost

    $6,443,976.86

    Main hallway

    Main street, December 2019

    Remodeled kitchen

    Remodeled kitchen, December 2019

    Remodeled kitchen

    Remodeled kitchen, December 2019

  • Upgrades/Refurbishments - Secondary

    Scroll down to view the following secondary school upgrade/ refurbishment bond projects:

    • Bowman Middle School
    • Jasper High School
    • Williams High School
    • Wilson Middle School

    Bowman Middle School

    2501 Jupiter Road, Plano, TX 75074

    • Architect: WRA Architects
    • Contractor: Cadence McShane
    • Plano ISD Construction Administrator: Quincy Lara

    Scope

    Provide a refurbishment and overall renewal of the existing school. The building will receive all new finishes throughout, including paint, carpet and tile. The existing kitchen also has been receiving a complete remodel with all new equipment.

    Timeline

    • Design Initiated: 5/2018
    • Design Completed: 12/2018
    • Construction Started: 3/2019
    • Construction Completed (Summer Refurbishment): 8/2019
    • Kitchen Completed: 11/2019

    Status

    Complete

    Construction Contract Amount

    $8,720,906

    Actual Construction Cost

    $8,596,821.42

    Serving line entry

    Serving line entry, December 2019

    Remodeled kitchen

    Remodeled kitchen, December 2019


    Jasper High School

    6800 Archgate Drive, Plano, TX 75024

    • Architect: Corgan
    • Contractor: Cadence McShane
    • Plano ISD Construction Administrator: Robert Dean

    Scope

    Provide a refurbishment and overall renewal of the existing school. The building will receive select new finishes throughout, including paint and tile. All restrooms will be updated with new tiles, partitions and fixtures. Dance will receive a new sprung wood dance floor. New athletic lockers. The design includes approximately 7,125 square feet of addition which consists of a new art room, new mat room and an enclosed back entry. 

    Timeline

    • Design Initiated: 6/2017
    • Design Completion: 2/2018
    • Construction Started: 3/2018
    • Construction Completed (Summer Refurbishment): 8/2018
    • Construction Completed Roof and Art: 12/2018
    • Construction Completed Mat Room: 3/2019

    Status

    Complete.

    Construction Contract Amount

    $10,891,928

    Actual Construction Cost

    $10,891,928

    New art room

    New art room, October 2019

    New enclosed back entry

    New enclosed back entry, October 2019


    Williams High School

    1818 18th Street, Plano, TX 75074

    • Architect: PBK Architects
    • Contractor: Lee Lewis Construction
    • Plano ISD Construction Administrator: Quincy Lara

    Scope

    To use current bond funds to build Phase 1, which would mesh seamlessly into a larger (Phase 2) renovation in the future, of a Long Range Facilities Master Plan.

    Phase 1 renovation will include relocating the main entry to the north side of the building, and providing a new entry feature and overall appearance. Major interior renovations will include a new administration suite, a new counselor suite, a new SPED suite, and new art labs totaling approximately 66,000 sf.

    Timeline

    • Design Initiated: 5/2018
    • Design Completed: 1/2021
    • Construction Started: 3/2021
    • Construction Completed: 7/2022

    Status

    Substantially complete.  The contractor continues to be on site after hours and on weekends to complete punch list items. Working on closeout documents.

    Construction Contract Amount

    $13,319,756

    Main Entry Vestibule
    Main Entry Vestibule - September 2022

    Classrooms/Corridor Under Construction    June 2022

    New Main Entry
    New Main Entry - September 2022


    Wilson Middle School

    1001 Custer Road, Plano, TX 75075

    • Architect: WRA Architects
    • Contractor: W.B. Kibler
    • Plano ISD Construction Administrator: Quincy Lara

    Scope

    Provide a refurbishment and overall renewal of the existing school. The building will receive all new finishes throughout, including paint, carpet and tile. Also, new teacher workstations. The existing kitchen also has been receiving a complete remodel with all new equipment.

    Timeline

    • Design Initiated: 6/2017
    • Design Completed:2/2018
    • Construction Started: 6/2018
    • Construction Completed (Summer Refurbishment): 8/2018
    • Kitchen and Classroom Casework Completed: 1/2019

    Status

    Complete.

    Construction Contract Amount

    $7,136,315

    Actual Construction Cost

    $7,333,130.38

    Additional funds were added for unforeseen conditions, which were not fully realized until the building structure was open.

    Classroom

    Classroom, September 2018

    Library, September 2018

    Library, September 2018

  • Enhancements - Secondary

    Scroll down to view bond secondary school enhancements:

    • Armstrong Middle School
    • Frankford Middle School
    • Plano ISD Academy High School
    • Rice Middle School
    • Renner Middle School
    • Vines High School

    Armstrong Middle School

    3805 Timberline Drive, Plano, TX 75074

    • Architect: PBK Architects
    • Contractor: Cadence McShane
    • Plano ISD Construction Administrator: Quincy Lara

    Scope

    The construction of a new band hall, and renovation of the existing fine arts suite. The completed project will have three distinct practice halls for band, choir and orchestra. 

    Timeline

    • Design Initiated: 3/2018
    • Design Completed: 10/2018
    • Construction Started: 2/2019
    • Construction Completed: 10/2019

    Status

    Complete

    Construction Contract Amount

    $5,049,956

    Actual Construction Cost

    $4,918,459.44

    Band hall addition

    Band hall addition, December 2019

    Interior staircase at addition

    Interior staircase at addition, December 2019


    Frankford Middle School

    7706 Osage Plaza Pkwy., Dallas, TX  75252

    • Architect: Corgan
    • Contractor: Cadence McShane
    • Plano ISD Construction Administrator: Robert Dean

    Scope

    The construction of a new band hall and renovation of the existing fine arts suite. The completed project will have three distinct practice halls for band, choir and orchestra.

    Timeline

    • Design Initiated: 4/2018
    • Design Completed: 10/2018
    • Scheduled Construction Start: 2/2019
      • Building Permit Delayed
    • Construction Started: 2/2020
    • Construction Completion: 8/2020

    Status

    Complete.

    Construction Contract Amount

    $5,120,383

    Actual Construction Cost

    $4,781,665.69

    New Addition

    New Addition, September 2020

    Interior of Fine Arts Suite

    Interior of Fine Arts Suite, September 2020


    Plano ISD Academy High School

    1701 Alma Drive, Plano, TX 75075

    • Architect: BLC Architecture
    • Contractor: Wilks Construction
    • Plano ISD Construction Administrator: Robert Dean

    Scope

    Remove the existing brick veneer, examine the existing cavity sheathing system and replace if necessary. Install new air barrier over sheathing, install new through-wall flashings at window and door heads and window sills.

    Timeline

    • Design Initiated: 10/2016
    • Design Completed: 3/2017
    • Construction Started: 5/2017
    • Construction Completed: 11/2017

    Status

    Complete.

    Construction Contract Amount

    $2,508,500

    Actual Construction Cost

    $2,480,298

    West elevation

    New brick at west elevation, October 2017

    New brick veneer

    New brick veneer, September 2018


    Renner Middle School

    5701 W. Parker Road, Plano, TX  75093

    • Architect: Corgan
    • Contractor: Cadence McShane
    • Plano ISD Construction Administrator: Robert Dean

    Scope

    The construction of a new band hall and renovation of the existing fine arts suite. The completed project will have three distinct practice halls for band, choir and orchestra. The campus will also receive upgrades to their kitchen serving line.

    Timeline

    • Design Initiated: 4/2018
    • Design Completed: 10/2018
    • Construction Started: 2/2019
    • Construction Completed: 8/2019

    Status

    Complete

    Construction Contract Amount

    $5,416,302

    Actual Construction Cost

    $5,274,689

    Band hall addition

    Band hall addition, October 2019

    Band hall interior

    Band hall interior, October 2019


    Rice Middle School

    8500 Gifford Drive, Plano, TX, 75025

    • Architect: Corgan
    • Contractor: Cadence McShane
    • Plano ISD Construction Administrator: Robert Dean

    Scope

    The construction of a new band hall and renovation of the existing fine arts suite. The completed project will have three distinct practice halls for band, choir and orchestra. The kitchen serving line is also being upgraded, along with all new carpet and VCT throughout the building.

    Timeline

    • Design Initiated: 4/2018
    • Design Completed: 10/2018
    • Construction Started: 3/2019
    • Construction Completed: 8/2019

    Status

    Complete

    Construction Contract Amount

    $6,038,497

    Actual Construction Cost

    $5,864,724

    Rice MS band hall addition

    Band hall addition, October 2019

    Band hall interior

    Band hall interior, October 2019


    Vines High School

    1401 Highedge Drive, Plano, TX 75075

    • Architect: PBK Architects
    • Contractor: Cadence McShane
    • Plano ISD Construction Administrator: Quincy Lara

    Scope

    A renovation of existing space to provide for three larger art rooms. In doing so a computer lab and Project Lead the Way will be displaced across the hall and re-established in the location art abandoned. Also doing an upgrade in the kitchen of select equipment and finishes.

    Timeline

    • Design Initiated: 3/2018
    • Design Completed: 10/2018
    • Construction Started: 6/2019
    • Construction Completed: 8/2019

    Status

    Complete

    Construction Contract Amount

    $3,277,183

    Actual Construction Cost

    $2,882,368.09

    Renovated art classroom

    Renovated art classroom, October 2019

    Renovated serving line

    Renovated kitchen serving line, October 2019

  • Enhancements - Stadiums/Turfs

    Scroll down to see bond turf/stadium enhancements:

    • Clark Stadium Fence Replacement
    • Phase I Turfs
    • Phase II Turfs
    • Phase III Turfs

    Clark Stadium Fence Replacement

    • Engineer: RLK
    • Contractor: Robinson Fence Company
    • Plano ISD Construction Administrator: Robert Dean

    Scope

    Replacement of existing chain link fencing surrounding the stadium, including swing gates and sliding gates, with wrought iron fencing and gates.  Replacement of chain link mesh along the north, south, east, and west sides of the existing concrete stadium seating. Structural design of new masonry fence columns along the fence adjacent to the south end of the stadium.

    Timeline

    • Design Initiated: 6/2020
    • Design Completed: 7/2020
    • Construction Started: 9/2020
    • Construction Completed: 1/2021

    Status

    Complete. 

    Construction Contract Amount

    $527,870

    Actual Construction Cost

    $529,87
    Added 42" tall stell fencing along the top of the south berm.

    New Columns and Fencing, September 2021

    New columns and fencing

    New Columns and Fencing, September 2021


    Phase I Turfs

    • Plano ISD Construction Administrator: Quincy Lara
    • Contractor (Three Student Activity Centers): Hellas Construction
    • Contractor (John Clark Stadium): FieldTurf

    Scope

    Replace the existing turf with new artificial turf at four locations. Those locations being the indoor student activity centers at each of the three senior highs, and the field at Clark Stadium.

    Timeline

    Construction Completed: 8/2017.

    Status

    The indoor fields are all complete. Clark Stadium is also complete. GMAX testing on all the new fields has been done.

    Actual Construction Cost

    Three indoor Student Activity Centers: $297,351
    John Clark Stadium: $310,183

    PSHS existing turf demo, May 2017

    Plano Senior High existing turf demo, May 2017

    PESH new turf installed

    Plano East new turf installment, June 2017


    Phase II Turfs

    • Engineer: RLK Engineering
    • Contractor: Hellas Construction
    • Plano ISD Construction Administrator: Quincy Lara

    Scope

    Replace the natural grass fields with artificial turf at four locations. Those locations being the track enclosed practice fields at each of the three senior highs, and at Williams Stadium. The project also includes resurfacing the tracks at Plano East, Plano Senior, and Williams Stadium.

    Timeline

    Construction from April 2017 – January 2018.

    Status

    Complete.

    Construction Contract Amount

    $4,516,750

    Actual Construction Cost

    $4,801,721.50

    Added a concrete curb around the perimeter of the running track, and a drainage flume on the NW corner of Williams Stadium. Repair of the existing running track sub-base at Plano Senior High School.

    PWSH new turf, Oct 2017

    Plano West new turf, October 2017

    PESH new turf Oct 2017

    Plano East new turf, October 2017


    Phase III Turfs

    • Engineer: RLK Engineering
    • Contractor: Hellas Construction
    • Plano ISD Construction Administrator: Quincy Lara

    Scope

    Replace the natural grass fields with artificial turf at the three Clark Stadium sub-varsity fields.

    Timeline

    Construction April-August 2018

    Status

    Complete.

    Construction Contract Amount

    $2,598,700

    Actual Construction Cost

    $2,579,617

    Sub varsity New Turf, Sept 2018

    Sub-varsity new turf, September 2018

    Sub-Varsity new turf, Sept 2018

    Sub-varsity new turf, September 2018

  • Enhancements - Kitchens/Serving Lines

    Scroll down to view bond kitchen & serving lines enhancements:

    • Kitchen Upgrades
    • Serving Line Upgrades

    Kitchen Upgrades (Hughston ES and Thomas ES)

    • Architect: Corgan
    • Contractor: ICI
    • Plano ISD Construction Administrator: Warren Kinsey

    Scope

    Complete remodel of the Hughston Elementary School kitchen with all new equipment and layout. Replacement of two serving lines at Thomas Elementary School. 

    Timeline

    • Design Initiated: 5/2019
    • Design Completed: 11/2019
    • Construction Started: 3/2020
    • Construction Completed: 8/2020

    Status

    Complete

    Construction Contract Amount

    $1,532,000

    Actual Construction Cost

    $1,465,445.29

    Hughston ES

    Hughston ES

    Thomas ES

    Thomas ES


    Serving Line Upgrades (Saigling ES, Shepard ES, Andrews ES, Hickey ES & Schimelpfenig MS)

    • Architect: PBK Architects
    • Contractor: MDI
    • Plano ISD Construction Administrator: Robert Dean

    Scope

    Serving line upgrades and select kitchen equipment replacement at Saigling ES, Shepard ES, Andrews ES, Hickey ES and Schimelpfenig MS. 

    Timeline

    • Design Initiated: 5/2019
    • Design Completed: 11/2019
    • Construction Started: 4/2020
    • Construction Completed: 8/2020

    Status

    Complete.

    Construction Contract Amount

    $1,575,900

    Actual Construction Cost

    $1,510,976.07

    Schimelpfenig

    Schimelpfenig MS

    Shepard

    Shepard ES

    Saigling

    Saigling ES

    Hickey

    Hickey ES

  • Portable Replacements

    Scroll down to view bond portable replacements: 

    Portable Replacements: $16,020,000. The 2008 bond funds were used in lieu of increasing the 2016 election. 

    • Guinn Special Programs Center
    • Plano East Senior High School
    • Wells Elementary School

    Guinn Special Programs Center

    2221 Legacy Drive, Plano, TX 75023

    • Architect: Perkins+Will
    • Contractor: Starling Richardson
    • Plano ISD Construction Administrator: Warren Kinsey

    Scope

    Provide an eight classroom addition to replace the two existing 4-classroom portables on site.

    Timeline

    • Design Initiated: 7/2016
    • Design Completed: 1/2017
    • Construction Started: 2/2017
    • Construction Completed: 8/2017

    Status

    Complete.

    Construction Contract Amount

    $3,375,278

    Actual Construction Cost

    $3,349,846.01

    Classroom additions

    Classroom addition, August 2017

    Classroom addition hallway

    Classroom addition hallway, December 2017


    Plano East Senior High School

    3000 Los Rios Boulevard, Plano, TX 75074

    • Architect: WRA Architects
    • Contractor: Cadence McShane
    • Plano ISD Construction Administrator: Quincy Lara

    Scope

    Provide a 16 classroom addition to replace the four existing 4-classroom portables on site. Through design the plan grew to add 21 classrooms plus a large meeting room for the staff. Project also includes a fully remodeled counselor suite.

    Timeline

    • Design Initiated: 8/2016
    • Design Completed: 4/2017
    • Construction Started: 5/2017
    • Construction Completed: 7/2018

    Status

    Complete.

    Construction Contract Amount

    $8,931,349

    Actual Construction Cost

    $8,485,608

    PESH new addition exterior

    New addition exterior, September 2018

    PESH additon interior

    New addition interior, June 2018


    Wells Elementary School

    3427 Mission Ridge Road, Plano, TX 75023

    • Architect: BLC Architecture
    • Contractor: Starling Richardson
    • Plano ISD Construction Administrator: Warren Kinsey

    Scope

    Provide a four classroom addition to replace the existing 4-classroom portable on site.

    Timeline

    • Design Initiated: 5/2016
    • Design Completed: 1/2017
    • Construction Started: 2/2017
    • Construction Completed: 8/2017

    Status

    Complete.

    Construction Contract Amount

    $2,102,821

    Actual Construction Cost

    $2,034,149.36

    Addition hallway

    Classroom addition hallway, August 2017

    playground

    New playground, August 2017

Executive Summary

  • The 2016 Plano ISD Facilities and Technology Task Force, bond executive summary was approved by the board approved on May 7, 2016.