2016 Bond Quarterly Construction Update
January - March 2023
Our Planning and Construction Department reports the progress of construction and renovation projects on a quarterly basis.
Administration
-
- Deputy Superintendent for Business & Employee Services, Johnny Hill
Facility Planning and Construction
-
- Executive Director of Facility Services, Juan Ramos
- Assistant Director of Facility Services, Tony Pearson
- Construction Manager, Johnny Pechacek
- Construction Administrator, Robert Dean
- Construction Administrator, Warren Kinsey
- Construction Administrator, Quincy Lara
2016 Bond, April-June 2022 Construction Status Report
-
New Construction
Scroll down to view bond new construction projects:
- Robbie & Lynore Robinson Fine Arts Center
- Early Childhood School 4
- Wraparound Services Center
- Clark JV Field Locker Room
Robbie & Lynore Robinson Fine Arts Center
1800 Alma Drive, Plano, TX 75075
- Architect: P+W/BORA
- Contractor: McCarthy
- Plano ISD Construction Administrator: Johnny Pechacek, Warren Kinsey
Scope
Provide a venue to showcase music, dance, theater and the visual arts. The facility will be approximately 82,200 SF spread across two levels. The main theater will have 1,500 seats and one balcony level. The building will also have a flexible 200 seat Studio Theater, large Rehearsal Room and Gallery component for exhibitions. Designed to host art contests, including University Interscholastic League (UIL) competitions with schools from outside of the district. The facility also has the potential to host outside performances and events, bringing art and culture from a variety of sources into the community of Plano.
Timeline
- Design Initiated: 2/2017
- Design Completed: 6/2018
- Construction Started: 1/2019
- Scheduled Construction Completion: TBD
- Construction Substantially Completed: 12/2022
- Floor Remediation Completed: 12/2022
- Exterior Wall Remediation Completed: TBD
Status
Substantially Complete
The grand opening of the Robbie & Lynore Robinson Fine Arts Center, originally scheduled for mid January, has been postponed. As construction has progressed, the floors in the building show evidence of significant cracking as a result of poor workmanship and/or design that do not meet the aesthetic standards established by Plano ISD. Mindful of our obligation to students, parents, staff, the taxpayers and the many supporters of this facility, Plano ISD leaders have elected not to take occupancy of the facility until this deficiency is resolved to the satisfaction of the District.
Understanding the ripple effect this has on our district and community, we will announce a new grand opening date as soon as we are able. Plano ISD students deserve a facility that honors their commitment to the arts and our goal is to make sure that you, our district and our community can be proud of our new home for the arts in Plano ISD.
Remediation
Floor remediation was completed in December. The District began to take over the building in late January, changing the locks, deep cleaning all areas, and moving in furniture. Mid to late March the Fine Arts Department started using the space for small UIL events and youth art month exhibits for elementary and secondary. A Grand Opening is anticipated for May.
The exterior wall remediation is still underway, and expected to be completed mid-April. A majority of the exterior has been painted with the elastomeric in a two tone color scheme proposed by the architect.
CONSTRUCTION CONTRACT AMOUNT
$54,015,932
Exterior Elastomeric Paint - March 2023
Art Gallery - March 2023
Early Childhood School 4
Mapleshade Lane, Dallas, TX 75252
- Architect: VLK Architects
- Contractor: Cadence McShane
- Plano ISD Construction Administrator: Warren Kinsey
Scope
Enlarge the capacity of the district's Early Childhood Program by constructing a fourth campus. The new school will be modeled after the Sara Isaacs Early Childhood School, but will also contain a kitchen and dining area. The building will be approximately 62,500 SF. Site conditions such as circulation, fire lanes, parking, landscape and irrigation will also be included in the work and overall planning.
Timeline
- Design Initiated: 6/2017
- Design Completed: 4/2018
- Voted Down By Board: 6/2018
Status
The Board requested further study on the district’s immediate need for a fourth early childhood school. To be brought forward at a subsequent time. Contracts with both the contractor and the architect have been closed.
The Wraparound Services Center is now scheduled to be built on this site.
Overall floor plan, June 2018
Main entry rendering, June 2018
Wraparound Services Center
Mapleshade Lane, Dallas, TX 75252
- Architect: VLK Architects
- Contractor: JC Commercial
- Plano ISD Construction Administrator: Robert Dean
Scope
Build a new, approximately 11,000 SF, facility to help serve the District in regards to Counseling and Academic Planning, Student Services, Community and Social Services, Family Engagement, and Health and Wellness. Site conditions such as traffic, fire lanes, parking, landscape and irrigation will also be included in the work and overall planning.
Timeline
- Design Initiated: 4/2021
- Scheduled Design Completion: 1/2022
- Scheduled Permit Release: TBD
- Scheduled Construction Start: TBD
- Scheduled Construction Completion: 365 days after permit
Status
JC Commercial was recommended, and approved at the 1/10/23 Board. The plans are currently with the City of Dallas awaiting the release of permit. Once released the contractor will start mobilizing on site. In the meantime they have started submittals, and buying out subcontracts.
Estimated Construction Amount
$5,550,777
View of site from NW corner, September 2021
Site plan, September 2021
Exterior Rendering, December 2021
Clark JV Locker Room
6600 Stadium Drive, Plano, TX 75023
- Architect: VLK Architects
- Contractor: ICI
- Plano ISD Construction Administrator: Robert Dean
Scope
The new masonry unit building is comprised of two separate athletic locker rooms, and one locker room for officials. New construction will include heating only, lighting and minimal electrical convenience power outlets.
Timeline
- Design Initiated: 6/2017
- Design Completed: 4/2018
- Construction Start: 3/2021
- Scheduled Construction Completion: 11/2021
- Construction Completed: 3/2022
Status
Complete
Estimated Construction Amount
$718,000
Actual Construction Cost
$714,422.10
New JV Fields Locker Room, March 2022
Interior View of Locker Room, March 2022
-
New Acquisitions
Scroll down to view new bond acquisition projects:
- Charmaine Solomon Adult Transition Center
- Employee Childcare 3
Charmaine Solomon Adult Transition Center
1631 Dorchester Dr., Plano, TX 75075
- Architect: PBK Architects
- Contractor: District Approved Vendors
- Plano ISD Construction Administrator: Warren Kinsey
Scope
- Phase 1 - Interior finish-out and building infrastructure upgrades to provide one center for all Special Education Transition Services for the District. Transition services are a coordinated set of activities designed as a results oriented process that promotes movement from school to post-school activities, including: post-secondary education, vocational training, integrated employment (including supported employment), continuing and adult education, adult services, independent living, or community participation.
- Phase 2 – Minor renovation of the kitchen and replacement of select kitchen equipment.
Timeline
- Building Purchased: 4/2017
- Previous Owner Moved Out: 5/2018
- Phase 1
- Construction Started: 6/2018
- Construction Completed: 8/2018
- Phase 2
- Construction Started: 6/2021
- Construction Completed: 8/2021
Status
Complete.
Construction Contract Amount:
- Phase 1: $700,000
- Phase 2: $510,850
Actual Construction Cost:
- Phase 1: $700,000
- Phase 2: $486,109.80
New monument sign, December 2019
Existing Kitchen, September 2020
Drywall Installation, June 2021
Underground Plumbing, June 2021
Employee Child Care 3
600 Old Custer Rd., Allen, TX 75013
- Contractor: District Approved Vendors
- Plano ISD Central Cluster Manager: Jason Wink
Scope
Renovate the recently purchased Montessori school and turn it into an Employee Child Care Center. Child Care Centers are licensed through the Texas Department of Family and Protective Services. The District’s Employee Child Care was created to provide a service for our teachers. The exceptional centers have proven to be a valuable tool in the retention and recruitment of the very best teachers in North Texas. This will be the District’s third employee child care.
Timeline
- Building Purchased: 8/2017
- Building Licensed: 6/2018
- Building Opened: 8/2018
Status
Complete.
Actual Construction Cost
$4,546,199
Interior rooms under construction, June 2018
Classroom view, March 2019
-
Added Capacity
Scroll down to view bond added capacity project for Gulledge Elementary.
Gulledge Elementary School
6801 Preston Meadow Drive, Plano, TX 75024
- Architect: WRA Architects
- Contractor: Lee Lewis Construction
- Plano ISD Construction Administrator: Quincy Lara
Scope
Provide a six classroom addition, along with associated site-work and paving.
Timeline
- Design Initiated: 6/2019
- Design Completion: 11/2019
- Construction Start: 3/2020
- Construction Completed: 10/2020
Status
Substantially Complete. Closeout documents being gathered.
Construction Contract Amount
$4,209,999
Actual Construction Cost
$4,049,571.94
New Classroom Hallway, September 2020
Classroom Addition, December 2020
Classroom Addition, December 2020
-
Major Renovations
Scroll down to view bond major renovation projects:
- Robinson Middle School
- Shepton High School
Robinson Middle School
6701 Preston Meadow Dr, Plano, TX 75024
- Architect: Corgan
- Contractor: Cadence McShane
- Plano ISD Construction Administrator: Robert Dean
Scope
Provide a major renovation of the existing campus. The design includes approximately 17,900 square feet of addition, and renovation of most of the school’s existing floor plan. The renovation looks to enlarge undersized classrooms, improve interior building circulation, remodel the kitchen, provide new finishes (flooring, paint and tile) throughout, improve upon the athletic locker room spaces, address major building systems (electrical, mechanical, plumbing), and install a new roof. It will also be the second school in the district to go geothermal.
Timeline
- Design Initiated: 3/2017
- Design Completed: 2/2018
- Construction Started: 3/2018
- Construction Completed: 8/2019
Status
Complete.
Construction Contract Amount
$27,971,729
Actual Construction Cost
$28,683,894.41
Additional funds were added for skylights, which were fully covered by insurance, and for fireproofing added per the City of Plano plan review comments.Remodeled kitchen, October 2019
Renovated science lab, October 2019
Shepton High School
5505 Plano Parkway, Plano, TX 75093
- Architect: VLK Architects
- Contractor: Pogue Construction
- Plano ISD Construction Administrator: Robert Dean
Scope
Provide a major renovation of the existing campus. The design consists of approximately 28,000 square feet of addition, and renovation of most of the school’s existing floor plan. The renovation looks to enlarge undersized classrooms, improve interior building circulation, remodel and expand the kitchen, enclose the cafetorium and acoustically treat it for performances, provide new finishes (flooring, paint and tile) throughout, improve upon the athletic locker room spaces, address major building systems (electrical, mechanical, plumbing), install a new roof, and improve the site drive lanes.
Timeline
- Design Initiated: 5/2016
- Design Completed: 3/2017
- Construction Started: 4/2017
- Construction Completed: 8/2018
Status
Complete.
Construction Contract Amount
$36,471,849
Actual Construction Cost
$36,471,849
Shepton High School entry, July 2019, photo credit: Chad Davis Photography
Collaboration space, photo credit: Chad Davis Photography
Student commons, July 2019
-
Upgrades/Refurbishments - Elementary Schools
Scroll down to see the following elementary school bond upgrade/refurbishment projects:
- Barksdale Elementary School
- Gulledge Elementary School
- Haggar Elementary School
- Haun Elementary School
- Miller Elementary School
- Skaggs Elementary School
Barksdale Elementary School
2424 Midway Road, Plano, TX 75093
- Architect: BLC Architecture
- Contractor: Starling Richardson
- Plano ISD Construction Administrator: Warren Kinsey
Scope
Provide a refurbishment and overall renewal of the existing school. The building will receive all new finishes throughout including paint, carpet and tile. Also new casework, new metal lockers, new ceiling tile and grid. The existing kitchen also receives a complete remodel with all new equipment. Two classrooms are also being added.
Timeline
- Design Initiated: 6/2017
- Design Completed: 2/2018
- Construction Started: 3/2018
- Construction Completed (Summer Refurbishment): 8/2018
- Kitchen and CR Addition Completed: 2/2019
Status
Complete.
Construction Contract Amount
$6,829,000
Actual Construction Cost
$6,744,824.71
Main hall, September 2018
Library, March 2019
Gulledge Elementary School
6801 Preston Meadow Drive, Plano, TX 75024
- Architect: WRA Architects
- Contractor: Starling Richardson
- Plano ISD Construction Administrator: Quincy Lara
Scope
Provide a refurbishment and overall renewal of the existing school. The building will receive all new finishes throughout including paint, carpet and tile. Also new casework, new metal lockers, new ceiling tile and grid. The existing kitchen also receives a complete remodel with all new equipment.
Timeline
- Design Initiated: 5/2016
- Design Completed: 10/2016
- Construction Started: 3/2017
- Construction Completed: 8/2017
- Kitchen Remodel Completed: 10/2017
- New Chillers Completed: 8/2018
Status
Complete. Project funds allowed for two new chillers to be added to the original scope of work.
Construction Contract Amount
$5,607,236
Actual Construction Cost
$5,636.290.70
Refurbished hallway, June 2017
New soils separator, September 2018
Haggar Elementary School
17820 Campbell Road, Dallas, TX 75252
- Architect: WRA Architects
- Contractor: Starling Richardson
- Plano ISD Construction Administrator: Warren Kinsey
Scope
Provide a refurbishment and overall renewal of the existing school. The building will receive all new finishes throughout including paint, carpet and tile. Also new casework, new metal lockers, new ceiling tile and grid. The existing kitchen also receives a complete remodel with all new equipment.
Timeline
- Design Initiated: 5/2016
- Design Completed: 10/2016
- Construction Started: 3/2017
- Construction Completed: 8/2017
Status
Complete.
Construction Contract Amount
$5,876,489
Actual Construction Cost
$5,528,189.06
Refurbished hallway, October 2017
Refurbished classroom pod, October 2017
Haun Elementary School
4500 Quincy Lane, Plano, TX 75024
- Architect BLC Architecture
- Contractor: Bartlett Cocke
- Plano ISD Construction Administrator: Warren Kinsey
Scope
Provide a refurbishment and overall renewal of the existing school. The building will receive all new finishes throughout including paint, carpet and tile. Also new casework, new metal lockers, new ceiling tile and grid. The existing kitchen also receives a complete remodel with all new equipment.
Timeline
- Design Initiated: 5/2018
- Design Completed: 11/2018
- Construction Started: 3/2019
- Construction Completed: 8/2019
Status
Complete
Actual Construction Cost
$7,313,358.25
Main street, December 2019
Dining, December 2019
Miller Elementary School
5651 Coventry, Richardson, TX 75082
- Architect: BLC Architecture
- Contractor: Starling Richardson
- Plano ISD Construction Administrator: Warren Kinsey
Scope
Provide a refurbishment and overall renewal of the existing school. The building will receive all new finishes throughout including paint, carpet and tile. Also new casework, new metal lockers, new ceiling tile and grid. The existing kitchen also receives a complete remodel with all new equipment.
Timeline
- Design Initiated: 6/2017
- Design Completed: 2/2018
- Construction Started: 3/2018
- Construction Completed: 8/2018
Status
Complete.
Construction Contract Amount
$5,989,000
Actual Construction Cost
$5,895,024.95
Main hall, March 2019
Library, March 2019
Skaggs Elementary School
3201 Russell Creek Drive, Plano, TX 75025
- Architect: BLC Architecture
- Contractor: Bartlett Cocke
- Plano ISD Construction Administrator: Warren Kinsey
Scope
Provide a refurbishment and overall renewal of the existing school. The building will receive all new finishes throughout including paint, carpet and tile. Also new casework, new metal lockers, new ceiling tile and grid. The existing kitchen also receives a complete remodel with all new equipment.
Timeline
- Design Initiated: 5/2018
- Design Completed: 11/2018
- Construction Started: 3/2019
- Construction Completed (Summer Refurbishment): 8/2019
- Kitchen Completed: 12/2019
Status
Complete
Construction Contract Amount
$6,632,771
Actual Construction Cost
$6,443,976.86
Main street, December 2019
Remodeled kitchen, December 2019
Remodeled kitchen, December 2019
-
Upgrades/Refurbishments - Secondary
Scroll down to view the following secondary school upgrade/ refurbishment bond projects:
- Bowman Middle School
- Jasper High School
- Williams High School
- Wilson Middle School
Bowman Middle School
2501 Jupiter Road, Plano, TX 75074
- Architect: WRA Architects
- Contractor: Cadence McShane
- Plano ISD Construction Administrator: Quincy Lara
Scope
Provide a refurbishment and overall renewal of the existing school. The building will receive all new finishes throughout, including paint, carpet and tile. The existing kitchen also has been receiving a complete remodel with all new equipment.
Timeline
- Design Initiated: 5/2018
- Design Completed: 12/2018
- Construction Started: 3/2019
- Construction Completed (Summer Refurbishment): 8/2019
- Kitchen Completed: 11/2019
Status
Complete
Construction Contract Amount
$8,720,906
Actual Construction Cost
$8,596,821.42
Serving line entry, December 2019
Remodeled kitchen, December 2019
Jasper High School
6800 Archgate Drive, Plano, TX 75024
- Architect: Corgan
- Contractor: Cadence McShane
- Plano ISD Construction Administrator: Robert Dean
Scope
Provide a refurbishment and overall renewal of the existing school. The building will receive select new finishes throughout, including paint and tile. All restrooms will be updated with new tiles, partitions and fixtures. Dance will receive a new sprung wood dance floor. New athletic lockers. The design includes approximately 7,125 square feet of addition which consists of a new art room, new mat room and an enclosed back entry.
Timeline
- Design Initiated: 6/2017
- Design Completion: 2/2018
- Construction Started: 3/2018
- Construction Completed (Summer Refurbishment): 8/2018
- Construction Completed Roof and Art: 12/2018
- Construction Completed Mat Room: 3/2019
Status
Complete.
Construction Contract Amount
$10,891,928
Actual Construction Cost
$10,891,928
New art room, October 2019
New enclosed back entry, October 2019
Williams High School
1818 18th Street, Plano, TX 75074
- Architect: PBK Architects
- Contractor: Lee Lewis Construction
- Plano ISD Construction Administrator: Quincy Lara
Scope
To use current bond funds to build Phase 1, which would mesh seamlessly into a larger (Phase 2) renovation in the future, of a Long Range Facilities Master Plan.
Phase 1 renovation will include relocating the main entry to the north side of the building, and providing a new entry feature and overall appearance. Major interior renovations will include a new administration suite, a new counselor suite, a new SPED suite, and new art labs totaling approximately 66,000 sf.
Timeline
- Design Initiated: 5/2018
- Design Completed: 1/2021
- Construction Started: 3/2021
- Construction Completed: 7/2022
Status
Substantially complete. The contractor continues to be on site after hours and on weekends to complete punch list items. Working on closeout documents.
Construction Contract Amount
$13,319,756
Main Entry Vestibule - September 2022Classrooms/Corridor Under Construction June 2022
New Main Entry - September 2022
Wilson Middle School
1001 Custer Road, Plano, TX 75075
- Architect: WRA Architects
- Contractor: W.B. Kibler
- Plano ISD Construction Administrator: Quincy Lara
Scope
Provide a refurbishment and overall renewal of the existing school. The building will receive all new finishes throughout, including paint, carpet and tile. Also, new teacher workstations. The existing kitchen also has been receiving a complete remodel with all new equipment.
Timeline
- Design Initiated: 6/2017
- Design Completed:2/2018
- Construction Started: 6/2018
- Construction Completed (Summer Refurbishment): 8/2018
- Kitchen and Classroom Casework Completed: 1/2019
Status
Complete.
Construction Contract Amount
$7,136,315
Actual Construction Cost
$7,333,130.38
Additional funds were added for unforeseen conditions, which were not fully realized until the building structure was open.
Classroom, September 2018
Library, September 2018
-
Enhancements - Secondary
Scroll down to view bond secondary school enhancements:
- Armstrong Middle School
- Frankford Middle School
- Plano ISD Academy High School
- Rice Middle School
- Renner Middle School
- Vines High School
Armstrong Middle School
3805 Timberline Drive, Plano, TX 75074
- Architect: PBK Architects
- Contractor: Cadence McShane
- Plano ISD Construction Administrator: Quincy Lara
Scope
The construction of a new band hall, and renovation of the existing fine arts suite. The completed project will have three distinct practice halls for band, choir and orchestra.
Timeline
- Design Initiated: 3/2018
- Design Completed: 10/2018
- Construction Started: 2/2019
- Construction Completed: 10/2019
Status
Complete
Construction Contract Amount
$5,049,956
Actual Construction Cost
$4,918,459.44
Band hall addition, December 2019
Interior staircase at addition, December 2019
Frankford Middle School
7706 Osage Plaza Pkwy., Dallas, TX 75252
- Architect: Corgan
- Contractor: Cadence McShane
- Plano ISD Construction Administrator: Robert Dean
Scope
The construction of a new band hall and renovation of the existing fine arts suite. The completed project will have three distinct practice halls for band, choir and orchestra.
Timeline
- Design Initiated: 4/2018
- Design Completed: 10/2018
- Scheduled Construction Start: 2/2019
- Building Permit Delayed
- Construction Started: 2/2020
- Construction Completion: 8/2020
Status
Complete.
Construction Contract Amount
$5,120,383
Actual Construction Cost
$4,781,665.69
New Addition, September 2020
Interior of Fine Arts Suite, September 2020
Plano ISD Academy High School
1701 Alma Drive, Plano, TX 75075
- Architect: BLC Architecture
- Contractor: Wilks Construction
- Plano ISD Construction Administrator: Robert Dean
Scope
Remove the existing brick veneer, examine the existing cavity sheathing system and replace if necessary. Install new air barrier over sheathing, install new through-wall flashings at window and door heads and window sills.
Timeline
- Design Initiated: 10/2016
- Design Completed: 3/2017
- Construction Started: 5/2017
- Construction Completed: 11/2017
Status
Complete.
Construction Contract Amount
$2,508,500
Actual Construction Cost
$2,480,298
New brick at west elevation, October 2017
New brick veneer, September 2018
Renner Middle School
5701 W. Parker Road, Plano, TX 75093
- Architect: Corgan
- Contractor: Cadence McShane
- Plano ISD Construction Administrator: Robert Dean
Scope
The construction of a new band hall and renovation of the existing fine arts suite. The completed project will have three distinct practice halls for band, choir and orchestra. The campus will also receive upgrades to their kitchen serving line.
Timeline
- Design Initiated: 4/2018
- Design Completed: 10/2018
- Construction Started: 2/2019
- Construction Completed: 8/2019
Status
Complete
Construction Contract Amount
$5,416,302
Actual Construction Cost
$5,274,689
Band hall addition, October 2019
Band hall interior, October 2019
Rice Middle School
8500 Gifford Drive, Plano, TX, 75025
- Architect: Corgan
- Contractor: Cadence McShane
- Plano ISD Construction Administrator: Robert Dean
Scope
The construction of a new band hall and renovation of the existing fine arts suite. The completed project will have three distinct practice halls for band, choir and orchestra. The kitchen serving line is also being upgraded, along with all new carpet and VCT throughout the building.
Timeline
- Design Initiated: 4/2018
- Design Completed: 10/2018
- Construction Started: 3/2019
- Construction Completed: 8/2019
Status
Complete
Construction Contract Amount
$6,038,497
Actual Construction Cost
$5,864,724
Band hall addition, October 2019
Band hall interior, October 2019
Vines High School
1401 Highedge Drive, Plano, TX 75075
- Architect: PBK Architects
- Contractor: Cadence McShane
- Plano ISD Construction Administrator: Quincy Lara
Scope
A renovation of existing space to provide for three larger art rooms. In doing so a computer lab and Project Lead the Way will be displaced across the hall and re-established in the location art abandoned. Also doing an upgrade in the kitchen of select equipment and finishes.
Timeline
- Design Initiated: 3/2018
- Design Completed: 10/2018
- Construction Started: 6/2019
- Construction Completed: 8/2019
Status
Complete
Construction Contract Amount
$3,277,183
Actual Construction Cost
$2,882,368.09
Renovated art classroom, October 2019
Renovated kitchen serving line, October 2019
-
Enhancements - Stadiums/Turfs
Scroll down to see bond turf/stadium enhancements:
- Clark Stadium Fence Replacement
- Phase I Turfs
- Phase II Turfs
- Phase III Turfs
Clark Stadium Fence Replacement
- Engineer: RLK
- Contractor: Robinson Fence Company
- Plano ISD Construction Administrator: Robert Dean
Scope
Replacement of existing chain link fencing surrounding the stadium, including swing gates and sliding gates, with wrought iron fencing and gates. Replacement of chain link mesh along the north, south, east, and west sides of the existing concrete stadium seating. Structural design of new masonry fence columns along the fence adjacent to the south end of the stadium.
Timeline
- Design Initiated: 6/2020
- Design Completed: 7/2020
- Construction Started: 9/2020
- Construction Completed: 1/2021
Status
Complete.
Construction Contract Amount
$527,870
Actual Construction Cost
$529,87
Added 42" tall stell fencing along the top of the south berm.New Columns and Fencing, September 2021
New Columns and Fencing, September 2021
Phase I Turfs
- Plano ISD Construction Administrator: Quincy Lara
- Contractor (Three Student Activity Centers): Hellas Construction
- Contractor (John Clark Stadium): FieldTurf
Scope
Replace the existing turf with new artificial turf at four locations. Those locations being the indoor student activity centers at each of the three senior highs, and the field at Clark Stadium.
Timeline
Construction Completed: 8/2017.
Status
The indoor fields are all complete. Clark Stadium is also complete. GMAX testing on all the new fields has been done.
Actual Construction Cost
Three indoor Student Activity Centers: $297,351
John Clark Stadium: $310,183Plano Senior High existing turf demo, May 2017
Plano East new turf installment, June 2017
Phase II Turfs
- Engineer: RLK Engineering
- Contractor: Hellas Construction
- Plano ISD Construction Administrator: Quincy Lara
Scope
Replace the natural grass fields with artificial turf at four locations. Those locations being the track enclosed practice fields at each of the three senior highs, and at Williams Stadium. The project also includes resurfacing the tracks at Plano East, Plano Senior, and Williams Stadium.
Timeline
Construction from April 2017 – January 2018.
Status
Complete.
Construction Contract Amount
$4,516,750
Actual Construction Cost
$4,801,721.50
Added a concrete curb around the perimeter of the running track, and a drainage flume on the NW corner of Williams Stadium. Repair of the existing running track sub-base at Plano Senior High School.
Plano West new turf, October 2017
Plano East new turf, October 2017
Phase III Turfs
- Engineer: RLK Engineering
- Contractor: Hellas Construction
- Plano ISD Construction Administrator: Quincy Lara
Scope
Replace the natural grass fields with artificial turf at the three Clark Stadium sub-varsity fields.
Timeline
Construction April-August 2018
Status
Complete.
Construction Contract Amount
$2,598,700
Actual Construction Cost
$2,579,617
Sub-varsity new turf, September 2018
Sub-varsity new turf, September 2018
-
Enhancements - Kitchens/Serving Lines
Scroll down to view bond kitchen & serving lines enhancements:
- Kitchen Upgrades
- Serving Line Upgrades
Kitchen Upgrades (Hughston ES and Thomas ES)
- Architect: Corgan
- Contractor: ICI
- Plano ISD Construction Administrator: Warren Kinsey
Scope
Complete remodel of the Hughston Elementary School kitchen with all new equipment and layout. Replacement of two serving lines at Thomas Elementary School.
Timeline
- Design Initiated: 5/2019
- Design Completed: 11/2019
- Construction Started: 3/2020
- Construction Completed: 8/2020
Status
Complete
Construction Contract Amount
$1,532,000
Actual Construction Cost
$1,465,445.29
Hughston ES
Thomas ES
Serving Line Upgrades (Saigling ES, Shepard ES, Andrews ES, Hickey ES & Schimelpfenig MS)
- Architect: PBK Architects
- Contractor: MDI
- Plano ISD Construction Administrator: Robert Dean
Scope
Serving line upgrades and select kitchen equipment replacement at Saigling ES, Shepard ES, Andrews ES, Hickey ES and Schimelpfenig MS.
Timeline
- Design Initiated: 5/2019
- Design Completed: 11/2019
- Construction Started: 4/2020
- Construction Completed: 8/2020
Status
Complete.
Construction Contract Amount
$1,575,900
Actual Construction Cost
$1,510,976.07
Schimelpfenig MS
Shepard ES
Saigling ES
Hickey ES
-
Portable Replacements
Scroll down to view bond portable replacements:
Portable Replacements: $16,020,000. The 2008 bond funds were used in lieu of increasing the 2016 election.
- Guinn Special Programs Center
- Plano East Senior High School
- Wells Elementary School
Guinn Special Programs Center
2221 Legacy Drive, Plano, TX 75023
- Architect: Perkins+Will
- Contractor: Starling Richardson
- Plano ISD Construction Administrator: Warren Kinsey
Scope
Provide an eight classroom addition to replace the two existing 4-classroom portables on site.
Timeline
- Design Initiated: 7/2016
- Design Completed: 1/2017
- Construction Started: 2/2017
- Construction Completed: 8/2017
Status
Complete.
Construction Contract Amount
$3,375,278
Actual Construction Cost
$3,349,846.01
Classroom addition, August 2017
Classroom addition hallway, December 2017
Plano East Senior High School
3000 Los Rios Boulevard, Plano, TX 75074
- Architect: WRA Architects
- Contractor: Cadence McShane
- Plano ISD Construction Administrator: Quincy Lara
Scope
Provide a 16 classroom addition to replace the four existing 4-classroom portables on site. Through design the plan grew to add 21 classrooms plus a large meeting room for the staff. Project also includes a fully remodeled counselor suite.
Timeline
- Design Initiated: 8/2016
- Design Completed: 4/2017
- Construction Started: 5/2017
- Construction Completed: 7/2018
Status
Complete.
Construction Contract Amount
$8,931,349
Actual Construction Cost
$8,485,608
New addition exterior, September 2018
New addition interior, June 2018
Wells Elementary School
3427 Mission Ridge Road, Plano, TX 75023
- Architect: BLC Architecture
- Contractor: Starling Richardson
- Plano ISD Construction Administrator: Warren Kinsey
Scope
Provide a four classroom addition to replace the existing 4-classroom portable on site.
Timeline
- Design Initiated: 5/2016
- Design Completed: 1/2017
- Construction Started: 2/2017
- Construction Completed: 8/2017
Status
Complete.
Construction Contract Amount
$2,102,821
Actual Construction Cost
$2,034,149.36
Classroom addition hallway, August 2017
New playground, August 2017
Executive Summary
-
The 2016 Plano ISD Facilities and Technology Task Force, bond executive summary was approved by the board approved on May 7, 2016.