• 2022 Bond Program Quarterly Update

    In November 2022, Plano ISD voters approved a $1.34 billion bond package and a Voter-Approval Tax Rate Election (VATRE). The bond will allow the district to update schools and facilities, add additional safety measures, build a much needed CTE center, add ADA-accessible playgrounds at all elementary schools and more (read more). For nearly a century, the Plano ISD community has shown a deep commitment to Plano schools. The 2022 bond election marks the 26th bond referendum passed by Plano ISD voters since 1923.

     Rendering of the main entrance for the new Plano ISD CTE Center  
    Pictured: Rendering of the primary entry of the new Career and Technical Education Center approved in the 2022 bond election.

Administration

    • Superintendent of Schools, Dr. Theresa Williams
    • Deputy Superintendent for Business & Employee Services, Johnny Hill

Facility Planning and Construction

    • Executive Director of Facility Services and New Construction, Juan Ramos
    • Director of Planning and New Construction, Tony Pearson
    • Construction Coordinator, Johnny Pechacek
    • Construction Administrator, Robert Dean
    • Construction Administrator, Quincy Lara
    • Construction Administrator, Oscar Mojica
    • Construction Administrator, Jimmy Bodies
    • Construction Assistant,  Carlesha Patterson
  • Maintaining Our Infrastructure

    Scroll down to view bond infrastructure construction projects:

    • Jupiter Center Renovation
    • Murphy Distribution Center Addition

    Jupiter Center Renovation

    2450 Jupiter Road, Plano Texas 75074

    • Architect: PBK
    • Contractor: McCown Gordon
    • Plano ISD Construction Administrator: Quincy Lara

    Scope

    The demolition of about 3,000 SF of interior office space, and the building back of approximately 7,000 SF of new interior office for Technology Deployment and Learning Media Services.  The existing facade will be updated to create a new entry point.  Site work includes new site fencing, motorized gates, and site lighting.  In addition, the existing roof will be replaced with a new roof system. 

    Timeline

    • Design Initiated: 8/2022
    • Design Completed: 2/2023
    • Construction Start: 3/2023
    • Scheduled Construction Completion: 4/2024

    Status

    Electrician is hanging and powering up light fixtures in the warehouse.  Painting touch ups are ongoing throughout the facility as well as painting the frames for the glass door lites.  Exterior stucco has been stripped.  Front wall to be reframed.  Installing LVT flooring and carpet throughout the office areas.  Millwork has been installed and sub is working on punch list items.  Technology is pulling low voltage wiring to the millwork.

    Sealing concrete floors in the warehouse.  Furniture has begun to arrive.

    Construction Contract Amount

    $2,796,000 

    Warehouse Floors Being Ground and Prepped for Sealing  3/1/24
    Warehouse Floors Being Ground and Prepped for Sealing 3/1/24 

    LVT Flooring and Carpet 3/1/24 
    LVT Flooring and Carpet 3/1/24 


    Murphy Distribution Center Addition

    650 N. Murphy Road, Murphy, Texas 75094                                           

    • Architect: PBK
    • Contractor: Taurus Commercial
    • Plano ISD Construction Administrator: Quincy Lara

    Scope

    The addition of approximately 15,900 SF of warehouse storage to the existing Murphy Distribution Center.  Work includes a new loading dock ramp, minor fencing modifications, and associated site work.  The addition also includes room for JROTC.          

    Timeline

    • Design Initiated: 8/2022
    • Design Completed: 2/2023
    • Construction Started: 3/2023
    • Scheduled Construction Completion: 4/2024

    Status

    Electrician is hanging and powering up light fixtures in the warehouse.  Painting touch ups are ongoing throughout the facility as well as painting the frames for the glass door lites.  Exterior stucco has been stripped.  Front wall to be reframed.  Installing LVT flooring and carpet throughout the office areas.  Millwork has been installed and sub is working on punch list items.  Technology is pulling low voltage wiring to the millwork.

    Sealing concrete floors in the warehouse.  Furniture has begun to arrive.

    Construction Contract Amount

    $3,545,114 


    Installing Masonry Veneer 3/1/24


    Storage Rack Installation 3/1/234 


  • Major Renovations

    Scroll down to view bond major renovation projects:

    • Williams High School
    • Plano Senior High School
    • Centennial Elementary 
    • Clark High School
    • Haggard Middle School

    Williams High School Phase 2 Renovation

    1818 18th Street, Plano, TX 75074

    • Architect: PBK Architects
    • Contractor: McCown Gordon 
    • Plano ISD Construction Administrator: Quincy Lara

    Scope

    The first phase of the overall master plan was completed under the 2016 Bond.  It included approximately 67,000 square feet of renovation to the Administration, Counseling, SPED, and Art areas.  The second phase under the current 2022 Bond will complete the master plan by renovating General Classrooms, CTE, Science, Library, Food Services-Cafeteria, Athletics, and Fine Arts.  The Field House will also be renovated including a roof replacement.  Site and drainage improvements will also be addressed.  The District will take ownership of the Harry Rowlinson Natatorium from the City and will renovate it .

    Timeline

    • Design Initiated: 2/2023
    • Design Completed: 12/2023
    • Expected Construction Started: 2/2024
    • Scheduled Construction Completed: 7/2026

    Status

    GMP was approved by the Board 1/16/24.  The contractor has mobilized on site  setting up their trailer and construction yard.  Temporary walls for Phase 1 have been installed, and demo of the Fine Arts area began on 3/4/24. 

    Construction Contract Amount

    $59,793,122

    Temporary Construction Walls closeupTemporary Construction Walls hallway
    Temporary Construction Walls 3/1/24

    Construction Trailer and Screening at South Entrance
    Construction Trailer and Screening at South Entrance 3/1/24


    Plano Senior High School

    2200 Independence Parkway, Plano, Texas 75075

    • Architect: Corgan
    • Contractor: CORE
    • Plano ISD Construction Administrator: Quincy Lara

    Scope

    Renovation of approximately 465,000 SF of existing buildings.  About 35,000 SF of addition for two new gym floors, weight room and locker room space.  Another 10,000 SF of new addition for front entry or where needed.  All buildings to be modernized, and major building systems upgraded.  Major remodel of Kitchen/Dining area. Campus will also receive updates to safety and security. Site athletic considerations include tennis court replacement/relocation along with storage and restrooms. Baseball and softball turf replacement, dugout extensions. 6’ wrought iron fence and gates around existing turf field and track. Auxiliary field LED lights.

    Timeline

    • Design Initiated: 7/2023
    • Anticipated Design Completed: 8/2024
    • Expected Construction Started: 11/2024
    • Scheduled Construction Completed: 7/2028

    Status

    Programming meetings are wrapping up.  The architect began putting schematic blocks together to see how the pieces might all fit.  Square footage being requested is still a challenge as we aim to balance what is needed with the budget.  An early package will need to be presented to the Board so the new softball field can be built before the old one is taken down to make way for Haggard.

    Estimated Construction Budget

    $197,210,000

    Proposed Lower Level Schematic
    Proposed Lower Level Schematic 3/1/24

    Existing Softball Needs to Move
    Existing Softball Needs to Move  3/1/24


    Early Childhood School Kitchen/Dining Additions

    • Architect: Glenn Partners
    • Contractor: MDI
    • Plano ISD Construction Administrator: Oscar Mojica

    Scope

    Kitchen/Dining room additions at each of the District’s three Early Childhood Schools.

    • Beaty ECS - 1717 Nevada Dr., Plano, Texas 75093
    • Isaacs ECS - 3400 E. Parker Rd., Plano, Texas 75074
    • Pearson ECS - 4000 Eagle Pass, Plano, Texas 75023

    Construction will also include HVAC Controls, new digital marquees, and new chillers at Beaty and Pearson.   

    Timeline

    Design Initiated: 8/2023
    Anticipated Design Completion: 4/2024
    Expected Construction Start: 6/2024
    Scheduled Construction Completion: 9/2025

    Status

    90% Construction Documents.  Initial 50% estimate needed a few clarifications which are anticipated will bring the numbers closer to budget.  Awaiting contractor’s 90% estimate.  Contractor is set to take out for bid with subs mid-April.  Will present a GMP to the Board May 21.     

    Estimated Construction Budget

     Beaty:        $4,961,883
    Isaacs:       $5,884,863
    Pearson:    $5,220,997

    Existing Isaacs Activity Room 12/1/23
    Existing Isaacs Activity Room 12/1/23

    Existing Beaty Dining
    Existing Beaty Dining 12/1/23


    Centennial Elementary School Kitchen Renovation/Addition

    2609 Ventura Drive, Plano, Texas 75093

    • Architect: Stantec
    • Contractor: JC Commercial
    • Plano ISD Construction Administrator: Oscar Mojica

    Scope

    Major remodel of the kitchen, including additional space if needed, including all new equipment.  Systems and compliance items include new electrical panels, fire alarm replacement, new digital marquee, new restroom partitions and some sidewalk repair.  Security recommendations include exterior door position contacts, and additional play area fencing if viable.  Also adding two sinks at the art room.

    Timeline

    • Design Initiated: 8/2023
    • Anticipated Design Completed: 2/2024
    • Expected Construction Started: 4/2024
    • Scheduled Construction Completed: 11/2024

    Status

    Opened bids February 13th from four bidders.  Evaluation team reviewed bids and recommended JC Commercial.  Anticipate starting construction in April.

    Estimated Construction Budget

    $3,062,777

    Recent Hughston ES Kitchen Remodel
    Recent Hughston ES Kitchen Remodel

    Recent Saigling ES Serving Line Upgrade
    Recent Saigling ES Serving Line Upgrade


    Clark High School Structural Repair/Renovation

    523 Spring Creek Parkway, Plano, Texas 75023

    • Architect: Corgan
    • Contractor: TBD (CSP)
    • Plano ISD Construction Administrator: Quincy Lara

    Scope

    Structural repairs of the special education area, two interior stairs, some sidewalks and a ramp along the east side of the building.  Also will look to replace the slabs and floors in both gyms.  In replacing the gym floors there is also the opportunity to follow athletic realignment.  Systems and compliance items include new controls, new cooling tower and some new RTUs.  Security recommendations include entry resistant film at main and secondary entries, emergency call stations, additional parking lot lighting, exterior door position contacts, and additional cameras.

    Timeline

    • Design Initiated: 8/2023
    • Anticipated Design Completed: 8/2024
    • Expected Construction Started: 10/2024
    • Scheduled Construction Completed: 8/2025

    Status

    Corgan walked the site with consultants to inspect the existing conditions back in late February.  Still anticipate issuing bid documents the end of summer of 2024.  The contractor will procure materials in the winter and spring with construction being completed over the summer of 2025.

    Estimated Construction Budget

    $3,738,508

    Replace Slabs in Both Gyms

    Replace Slabs in Both Gyms

    Sidewalk Repair Needed
    Sidewalk Repair Needed


    Haggard Middle School Replacement

    2832 Parkhaven Drive, Plano, Texas 75075

    • Architect: VLK
    • Contractor: CORE
    • Plano ISD Construction Administrator: Quincy Lara

    Scope

    Construction of a new Haggard Middle School (Grades 6-8) approximately 187,900 SF.  It will be built on the existing site to replace the current campus. The existing building will remain in use during the construction of the project, and great care will be given to protect and maintain the present site, building, services, infrastructure, security and access.  Once the new building is complete the existing will be demolished.  Site conditions such as circulation drives, fire lanes, parking, and landscape/irrigation will be included in the work and overall plan along with a new 4-lane synthetic track. 

    Timeline

    • Design Initiated: 7/2023
    • Anticipated Design Completed: 11/2024
    • Expected Construction Started: 2/2025
    • Scheduled Construction Completed:
      • New Building, paving and drives: 7/2026
      • Demo of the existing building, and building of new Track: 12/2026

    Status

    75% Construction Documents.  Anticipate bidding in November, and recommending a GMP to the January Board.  Construction to begin February 2025.

    Estimated Construction Budget

    $90,000,000

    Haggard Middle School Site Map
    Proposed Site Plan 6/1/24

    Rendering of New Main Entry (View from Parkhaven) 9/30/24
    Rendering of New Main Entry (View from Parkhaven) 9/30/24

  • Minor Renovations

    Scroll down to view bond major renovation projects:

    • Plano West Senior High School
    • Plano East Senior High School

    Plano West Senior High School Building A Renovation

    5601 W. Parker Road, Plano, Texas 75093

    • Architect: Glenn Partners 
    • Contractor: Hill & Wilkinson  
    • Plano ISD Construction Administrator: Oscar Mojica 

    Scope

    Renovation of Building A approximately 145,000 SF including elevator replacement.  Also the removal of 22 operable partition walls in Buildings A and B with solid walls scheduled to be put back in their place.  Campus will also receive an upgrade to the chiller plant and HVAC controls.  About 35,000 SF of addition for two new gym floors, weight room and locker room space.  Campus will also receive updates to safety and security. Site athletic considerations include tennis court replacement/relocation along with storage and restrooms. Baseball and softball dugout extensions.  Auxiliary field LED lights.  Theatrical rigging upgrade in Fine Arts.

    Timeline

    • Design Initiated: 7/2023
    • Anticipated Design Completed: 6/2024
    • Expected Construction Started: 8/2024
    • Scheduled Construction Completed: 8/2026

    Status

    100% Design Development is currently in review.  The architect recently introduced the proposed color palette along with some interior perspectives.  Moving into Construction Documents.   

    Estimated Construction Budget

    $83,433,722

    Conceptual Site Plan Conceptual Site Plan key
    Conceptual Site Plan 12/1/23

    Conceptual Rendering of New Athletic Entry
    Conceptual Rendering of New Athletic Entry 12/1/23


    Material & Finish Palette 3/1/24


    Rendering of Proposed Main Lobby 3/1/24


    Rendering of Proposed Practice Gym 3/1/24

    Rendering of Proposed Training Room
    Rendering of Proposed Training Room

    Rendering of Proposed Locker Room
    Rendering of Proposed Locker Room 3/1/24


    Plano East Senior High School Building D Renovation

    3000 Los Rios Boulevard, Plano, Texas 75074

    • Architect: WRA
    • Contractor: Cadence McShane
    • Plano ISD Construction Administrator: Robert Dean

    Scope

    Renovation of Building D approximately 7,000 SF.  Ceiling and lights in Buildings B1, B2, B3 and B4.  Upgrade to chiller plant and HVAC controls.  Addition of 35,000 SF for two new gym floors, weight room and some locker room space.  Locker room major renovation.  Site athletic considerations include tennis court replacement/relocation along with storage and restrooms.  Baseball and softball locker rooms with dugout extensions.  Auxiliary field LED lights.  Add restrooms and water to Student Activity Center.  Campus will also receive updates to safety and security.  CTE needs an expanded Consumer Science Lab classroom.  Marching band tower.    

    Timeline

    • Design Initiated: 7/2023
    • Anticipated Design Completed: 8/2024
    • Expected Construction Started: 11/2024
    • Scheduled Construction Completed: 11/2026

    Status

    Design Development is continuing.  Pre-construction meetings with the contractor are occurring to make sure we are still within budget, and to start discussing schedule and how to phase the work.

    Estimated Construction Budget

    $48,459,610

    Conceptual Rendering of Lobby and GymnasiumConceptual Rendering of Lobby and Gymnasium key
    Conceptual Rendering of Lobby and Gymnasium 12/1/23

    Proposed Additional Gym Floors  Proposed Additional Gym Floors Entrance
    Proposed Additional Gym Floors 12/1/23

    Proposed Additional Gym InteriorProposed Additional Gym InteriorProposed Additional Gym InteriorProposed Additional Gym Interior

  • CTE and Innovative Programs

    Scroll down to view bond CTE and Innovative Programs projects:

    • Career and Technical Education Center

    Career and Technical Education Center

    • Architect: Huckabee
    • Contractor: Joeris
    • Plano ISD Construction Administrator: Robert Dean

    Scope

    Construction of a new Career and Technical Education Center approximately 120,000 SF.  The Career and Technical Education (CTE) Center will offer students the academic and relevant technical skills, knowledge and training necessary to prepare for further education and careers in current or emerging professions.  The center will be a state-of-the-art facility with real-world learning spaces, and equipment for students 9th-12th.  Circulation, fire lanes, parking, and landscape/irrigation will be examined and included in the work and overall plan. 

    Timeline

    • Design Initiated: 7/2023
    • Anticipated Design Completion: 8/2024
    • Expected Construction Start: 10/2024
    • Scheduled Construction Completion: 6/2026

    Status

    Huckabee recently presented their Schematic Design (SD) to the Board at the February 13th work session.  The project has officially moved into Design Development (DD).  Meetings will continue with leadership and CTE to continue to flesh out the details needed for each area of study. Cosmetology was recently added as a career pathway.

    Estimated Construction Budget

    $76,665,600 

    Proposed Site Plan
    Proposed Site Plan 3/1/24

    Precedent Images collage of 3 images

    Precedent Images 3/1/24 

    Rendering of Secondary Entry
    Rendering of Secondary Entry 3/1/24

    Rendering of Primary Entry
    Rendering of Primary Entry 3/1/24

  • Enhancements - Campus Athletics

    Scroll down to see bond athletics enhancements:

    • Plano East and West Track Fencing
    • Plano East Baseball & Softball Turf
    • Plano West Baseball & Softball Turf
    • Middle School Tracks - Phase 1

    Plano East and West Track Fencing

    • Engineer: RLK
    • Contractor: Robinson Fence Company
    • Plano ISD Construction Administrator: Robert Dean

    Scope

    Removal of existing 4’ chain link fence, fence posts, mow strip, and gates, and installation of new 6’ ornamental fence, fence posts, gates, and mow strip around the perimeter of the competition running tracks and turf football fields at Plano East Senior High School and Plano West Senior High School.

    Timeline

    • Design Initiated: 3/2023
    • Design Completed: 6/2023
    • Construction Started: 7/2023
    • Construction Completed: 12/2023

    Status

    Substantially complete. Fencing and gates are 100% complete.  Some irrigation repair at both campuses remains.  

    Construction Contract Amount

    Plano East: $255,550
    Plano West: $278,750


    Plano East Baseball & Softball Turf

    • Engineer: RLK
    • Contractor: Hellas 
    • Plano ISD Construction Administrator: Robert Dean

    Scope

    Provide new synthetic turf at both the baseball and softball fields.   The existing baseball currently has turf in the infield, and grass in the outfield.  The existing softball has dirt in the infield, and turf in the outfield.  This project will look to install new turf on the entirety of both fields (infields and outfields alike).  A Change Order approved in October added a metal outfield fence for baseball.

    Timeline

    • Design Initiated: 5/2023
    • Design Completed: 8/2023
    • Construction Started: 9/2023
    • Construction Completed: 1/2024

    Status

    Substantially complete.

    Construction Contract Amount

    $2,720,900

    Change Order 1 Cost

    $149,577

    Total Cost

    $2,870,477

    New Baseball and Softball Turf at Plano East
    New Baseball and Softball Turf at Plano East 3/1/24


    Plano West Baseball & Softball Turf

    • Engineer: RLK
    • Contractor: Paragon
    • Plano ISD Construction Administrator: Robert Dean

    Scope

    Provide new synthetic turf at both the baseball and softball fields.   The existing baseball currently has turf in the infield, and grass in the outfield.  The existing softball has dirt in the infield, and turf in the outfield.  This project will look to install new turf on the entirety of both fields (infields and outfields alike).  A Change Order approved in October added a metal outfield fence for softball.     

    Timeline

    • Design Initiated: 5/2023
    • Design Completed: 8/2023
    • Construction Started: 9/2023
    • Construction Completed: 1/2024

    Status

    Substantially Complete. 

    Construction Contract Amount

    $2,736,500

    Change Order 1 Cost

    $90,625

    Total Cost

    $2,827,125

    New  Baseball and Softball Turf at Plano East                                         3/1/24

    New Baseball and Softball Turf at Plano West  New Baseball and Softball Turf at Plano West
    New Baseball and Softball Turf at Plano West 3/1/24


    Middle School Tracks - Phase 1

    • Engineer: RLK
    • Contractor: Hellas
    • Plano ISD Construction Administrator: Robert Dean

    Scope

    Provide new, all weather, synthetic tracks at Bowman MS, Wilson MS, and Robinson MS.  Ideally a 400m 4-Lane track, but if site constraints don’t allow it a smaller 300m 4-lane to be installed.           

    Timeline

    • Design Initiated: 3/2023
    • Design Completed: 8/2023
    • Construction Started: 11/2023
    • Construction Completed: 4/2024

    Status

    Robinson MS playfield is ready for sod, irrigation is 85% complete. Track Surfacing is ongoing with anticipated completion 3/20.  At Wilson asphalt substrate is complete.  Haul off of soil is ongoing.  Substantial completion 4/15.  Bowman haul off of materials is ongoing.  Topsoil is ongoing.  Irrigation to begin early March.  Track surfacing to follow Robinson’s completion.

    Construction Contract Amount

    Bowman: $1,484,465
    Robinson: $2,182,675
    Wilson: $1,878,485

    Robinson Track Surfacing
    Robinson Track Surfacing 3/1/24

    Wilson Track Asphalt Substrate
    Wilson Track Asphalt Substrate 3/1/24


    Middle School Tracks - Phase 2

    • Engineer: RLK
    • Contractor: TBD
    • Plano ISD Construction Administrator: 

    Scope

    Timeline

    • Design Initiated: 
    • Design Completed: 
    • Construction Started: 
    • Construction Completed: 

    Status

    Estimated Budget: $4,000,000

    Frankford: 
    Hendrick: 
    Murphy: 

  • Enhancements - Safety and Security

    Scroll down to view bond safety and security enhancements:

    • Classroom Doors & Entry Resistant Film

    Classroom Doors & Entry Resistant Film (Elementary Schools, Early Childhood Schools, Early Childcare Centers)

    • Architect: WRA
    • Contractor: Gliden Industries
    • Plano ISD Construction Administrator: Robert Dean/Quincy Lara

    Scope

    Add classroom doors to all elementary school classrooms currently without a door.  Add entry resistant film on main vestibules, secondary entries and all windows. Modify all existing classroom door hardware to storeroom function.  The project covers 44 elementary schools and includes the installation of about 730 doors, and 126,000 SF of film.  A change order in June added scope to the project to include entry resistant film at our three early childhood schools and two early childcare centers.

    Timeline

    • Design Initiated: 3/2023
    • Design Completed: 5/2023
    • Construction Started: 62023
    • Construction Completed: 11/2023

    Status

    Substantially complete.  The contractor will continue to work through the fall break to wrap up punch list items.  The installation of entry resistant film at the Pebble Creek Early Childcare Center 1 will be ongoing.  The existing window frames and doors are residential, and need to be replaced in order to accept the film and meet design intent.  Details for the door and window replacement are being developed, and work is anticipated to be begin in June of 2024.

    Construction Contract Amount

    $6,755,000

    Change Order 1 Cost

    $318,030

    Total Cost

    $7,073,030

  • Playgrounds

    ADA Playground

    • Aldridge Elementary
    • Barksdale Elementary
    • Bethany Elementary
    • Brinker Elementary
    • Carlisle Elementary
    • Hughston Elementary
    • Meadows Elementary
    • Stinson Elementary
    • Barron Elementary
    • Dooley Elementary
    • Hickey Elementary
    • Andrews Elementary
    • Saigling Elementary
    • Mathews Elementary
    • Skaggs Elementary
    • Mitchell Elementary
    • Daffron Elementary

    Playgrounds - Phase 1

    • Engineer: CEI
    • Contractor: Innovative Sport Surfacing 
    • Plano ISD Construction Administrator: Robert Dean

    Scope

    Provide new, all weather, ADA accessible, upper unit playgrounds with sunshade canopy at Aldridge ES, and Stinson ES.

    Timeline

    • Design Initiated: 3/2023
    • Anticipated Design Completed: 6/2023
    • Expected Construction Start: 9/2023
    • Scheduled Construction Completion 4/2024

    Status

    The playground equipment at Aldridge and Stinson are both 95% complete.  Currently preparing the subgrade for turf installation.  Work on the shade structure is ongoing at both locations.

    Estimated Construction Budget

    Aldridge: $311,985
    Stinson: $311,985

    Aldridge Site Prep for Upper Unit Playground
    Aldridge Site Prep for Upper Unit Playground 12/1/23

    Stinson Playground Equipment and Canopy Install
    Stinson Playground Equipment and Canopy Install 3/1/24


    Playgrounds - Phase 1

    • Engineer: RLK
    • Contractor: We Build Fun 
    • Plano ISD Construction Administrator: Robert Dean

    Scope

    Provide new, all weather, ADA accessible, lower and upper unit playgrounds with sunshade canopy at Bethany ES, Hughston ES, Barksdale ES, Meadows ES, Carlisle ES and Brinker ES.           

    Timeline

    • Design Initiated: 3/2023
    • Anticipated Design Completed: 8/2023
    • Expected Construction Start: 11/2023
    • Scheduled Construction Completion 6/2024

    Status

    Carlisle equipment and canopy are complete.  Turf installation started first week of March.  Brinker curbs and sidewalks have been installed.  Rough grading is ongoing.  Playground equipment has begun.  At Bethany fencing has been established and demo has begun.  Barksdale utilities are being marked.  Meadows and Hughston are being surveyed. 

    Estimated Construction Budget

    Barksdale: $599,990                   Hughston: $599,990
    Meadows: $602,392                    Carlisle: $628,638
    Bethany: $599,990                      Brinker: $599,990

    Carlisle Playground Equipment and Canopy
    Carlisle Playground Equipment and Canopy 3/1/24

    Brinker Rough Grading
    Brinker Rough Grading 3/1/24


    Playgrounds - Phase 2

    • Engineer: RLK
    • Contractor: TBD
    • Plano ISD Construction Administrator: 

    Scope

    Timeline

    • Design Initiated: 
    • Design Completed: 
    • Construction Started: 
    • Construction Completed: 

    Status

    Estimated Budget: $4,800,000

    Barron: 
    Dooley:
    Hickey:
    Andrews:
    Saigling:
    Mathews:
    Skaggs:
    Mitchell:
    Daffron:

  • Systems and Compliance

    Systems and Compliance - Phase 1

    PROJECT

    ARCH/ENG

    CONTRACTOR
    (Board Approved)

    CONTRACT AMOUNT

    COMPLETION

    Andrews ES HVAC Upgrades

    EMA

    Infinity (12/12/23)

    $1,608,791

    8/2024, exterior work 11/2024

    Aldridge ES S&C

    WRA

    Gliden (1/16/24)

    $4,631,250

    8/2024

    Administration Building S&C 

    Corgan

    MDI (3/19/24)

    $5,800,000 (est. budget)

    TBD

    Plano West Switchboard

    RWB

    Able Elec. (6/20/23)

    $141,540

    7/2024

  • Phase 2

    Phase 2

    PROJECT

    ARCH/ENG
    (Board Approved)

    CONTRACTOR 

    Estimated Construction Budget

    Transportation Building Addition/Renovation

     (4/2/24)

    TBD 

    $14,000,000 (est. budget)

    Transportation Fueling Station

    (4/2/24)

    TBD

    1,600,000 (est. budget)

    Service Center Renovation

     (4/2/24)

     TBD

    $14,500,000 (est. budget)

    Frankford Middle School Kitchen Addition/Renovation


    (4/2/24)

    TBD

    $6,600,000 (est. budget)

    Hightower Elementary School Kitchen Addition/Renovation

    (4/2/24)

    TBD

    $2,400,000 (est. budget)

    Systems and Compliance Phase 2
    (McMillen, Haun, Bird Center, Clark Stadium, Bethany, Hedgcoxe, Hendrick,Mitchell)

    3/19/24

    TBD

    $8,898,000 (est. budget)